www.onicon.com
SYSTEM-40 BTU MEASUREMENT SYSTEM
Back View
Side view
Side View
Side View
Front view
Side view
Front view
Side view
Side view
3.3.5 Orientation
Orient the ½” - 1” meters as shown below. The meter may be installed with
upward or downward flow in vertical pipes in closed loop pressurized systems.
Avoid any installation locations where the pipe may not be completely full.
Orient the 1¼" - 2½" meters as shown below. The meter may be installed with
upward or downward flow in vertical pipes in closed loop pressurized systems.
Avoid any installation locations where the pipe may not be completely full.
The flow sensor is installed with threaded meter couplings and flat sealing
gaskets as shown below. Orient the sensor body by aligning the flow direction
arrow with the direction of flow in the pipe.
IMPORTANT NOTE
Do not orient meters as shown above where air can become trapped in
the piping system.