Lower Port:
The lower port allows for the expansion of the reserve high pressure cylinder bank
beyond the two cylinders that are included in the frame of the machine. From this port,
an auxiliary high pressure manifold can be connected, increasing the size of the reserve
bank by 3, 4, etc. additional cylinders. These additional high pressure reserve manifolds
along with extra cylinders are available from
OGSI. See drawing below for suggested
layout.
High
Pressure
Set-up
Upper Port
Low Pressure
Set-up
Lower Port