39
Figure 40: Tilt Valve Calibration Screens
9.
Select the Enter button (A) to begin calibration.
10.
Follow the instructions on screens 1 – 3 then press the Enter button (B).
11.
Follow instructions on screen 4 then press the Cal icon (C).
12.
When the calibration is complete, press the Enter button (D) to exit calibration.
13.
Table 2 shows examples of “before” and “after” calibration values. The new values should
be slightly higher to account for the additional UC5 wiring on the John Deere valve.
Table 2: Calibration Value Examples
Function Calibration
before
UC5
Installed
Calibration after UC5
Installed
Left Up
550
860
Left Down
600
910
Right Up
620
860
Right Down
620
900
14.
Test Autofold and confirm that it is functioning properly. If it is not, repeat the calibration
procedure.
B
D
C
Summary of Contents for UC5 Topcon X30
Page 1: ...John Deere R Series Active Wing Roll Control Installation Manual JD12A ...
Page 7: ...4 4 Kit Parts 4 1 Kit Overview Figure 2 JD12A System Parts ...
Page 8: ...5 4 2 Hydraulic Plumbing Figure 3 JD12A Hydraulic Plumbing ...
Page 25: ...22 Figure 20 Valve Block Solenoid Locations ...
Page 29: ...26 Figure 23 Load Sense Bleed Orifice Location on Top of Block Remove this coil ...
Page 45: ...42 12 5 ITEM C10 43230 04 CABLE UC5 VALVE DT TO DT ...
Page 46: ...43 12 6 ITEM C20 43240 41 CABLE UC5 INTERFACE TILT DT R4038 ...
Page 47: ...44 12 7 ITEM C21 43240 38 CABLE UC5 INTERFACE JOHN DEERE R4030 4038 ML ...
Page 48: ...45 12 8 ITEM C30 43250 07 CABLE UC5 BATTERY JD FUSED ...