33
11
Software Setup
1.
Start up the sprayer and test the sprayer’s functionality. The display terminal does not need
to be powered on for the original boom function switches to operate. Unfold the booms
and raise/lower each boom and the main section.
Confirm that the cabling and hoses are agreeable to the entire range of motion.
2.
If any functions do not work, review the hydraulic and electrical portions of this manual to
check for proper installation.
3.
Turn on the power for the display terminal using the switch on the side.
4.
The procedure for the installation of the UC5 Spray Height Control system is now
complete. Begin the AUTOMATIC SYSTEM SETUP procedure as described in the UC5
Spray Height Control Operator’s Manual.
5.
After the installation has been performed the following procedures must be performed to
recalibrate the JD tilt functions.
11.1
Wing Roll Cylinder Air Bleed Procedure
After installing the Wing Roll Cylinder, air will have to be removed from the system. The following is a
step by step procedure for bleeding air from the system using both the sprayer joystick and the
NORAC manual valve drive screen.
If an AgLeader proprietary display is being used to operate the NORAC Boom Height Control, proceed
to Section 11.1.2 for the procedure.
11.1.1
Using a Virtual Terminal (VT) or PULSE
TM
Display
1.
Remove the air from the tilt cylinders, using the sprayer’s joystick controls.
a)
Move the left tilt cylinder full stroke three times.
b)
Move the right tilt cylinder full stroke three times.
2.
The NORAC screen on the VT or PULSE must be used to remove air from the roll
channel:
a)
Start an Automatic Install.
i)
If this is a new install, the system will automatically start an automatic install.
ii)
If an install has already been performed, follow the icons in step 3 to start the install.
b)
Select the appropriate sprayer make and model on the screen.
c)
Read the disclaimer menus and move through the screens.
d)
At the screen reading “level the boom at 35in”, press the button with a house on it to exit the
install and return to the main run screen.
Summary of Contents for UC5 Topcon X30
Page 1: ...John Deere R Series Active Wing Roll Control Installation Manual JD12A ...
Page 7: ...4 4 Kit Parts 4 1 Kit Overview Figure 2 JD12A System Parts ...
Page 8: ...5 4 2 Hydraulic Plumbing Figure 3 JD12A Hydraulic Plumbing ...
Page 25: ...22 Figure 20 Valve Block Solenoid Locations ...
Page 29: ...26 Figure 23 Load Sense Bleed Orifice Location on Top of Block Remove this coil ...
Page 45: ...42 12 5 ITEM C10 43230 04 CABLE UC5 VALVE DT TO DT ...
Page 46: ...43 12 6 ITEM C20 43240 41 CABLE UC5 INTERFACE TILT DT R4038 ...
Page 47: ...44 12 7 ITEM C21 43240 38 CABLE UC5 INTERFACE JOHN DEERE R4030 4038 ML ...
Page 48: ...45 12 8 ITEM C30 43250 07 CABLE UC5 BATTERY JD FUSED ...