5. Operation
5.5.11 Restart HMI
The function is used for restart the HMI.
6. Commissioning
6.1 Preparation of Commissioning
Ensure all the devices are accessible for operation, maintenance and service.
Check and confirm that the inverter is firmly installed.
Space for ventilation is sufficient for one inverter or multiple inverters.
Nothing is left on the top of the inverter or battery module.
Inverter and accessories are correctly connected.
Cables are routed in safe place or protected against mechanical damage.
Warning signs and labels are suitably affixed and durable.
6.2 Commissioning Procedure
If all the items mentioned above meet the requirements, proceed as follows to start up the
inverter for the first time.
6.2.1 Switch on the AC-backup and AC-grid.
6.2.2 Follow the picture below to select grid standard.
6.2.3 Switch on the DC circuit breaker between inverter and battery.
6.2.4 (Optional) When the battery equipped is Pylon Li-ion Battery,
or BYD battery, turn on the switch on the battery manually.
6.2.5 The relay will make 'clicking' sounds and it will take a short-time
to work automatically.
6.2.7 The system will work properly.
This function is applicable by maintenance personnel only, wrong
operation will prevent the inverter from working properly.