Initial Energization
78
Prior to energizing all three (3) phases, it is advised to energize phase-C only.
Energizing phase-C allows for the following two (2) commissioning steps to be
performed:
Overview of Commissioning Steps:
1. Phase-C powers the control power PT, energizing the control cabinet
2. Phase-C identification from Interconnection, through the test-switches, to the Meter
& Protective Relay
For the following steps, the myPV ClearSky™ PLUS’s Control Panel door will need to
be opened and the dead front swung open to allow for AC power measures.
Energization Steps:
1. Instruct the MV contractor to energize phase-C, as it is labeled at the
interconnection
2. In the Control Cabinet, use a Multimeter (set to AC RMS) to verify the presence of
~120V AC voltage (±10%, 108 - 132V) at locations (A) 602A [FU3] and (B) [either
10A]
[PASS] If ~120V AC is present., phase-C has been verified and control power
commissioning may begin. Proceed to Control Power Commissioning.
[FAIL] If ~120V AC is not present, phase-C has not been verified, and corrective
actions are required. Please consult your MV contractor, or Solar-Ops for
additional support. Do Not Proceed.
3. If [PASS] where ~120V AC is present In both locations:
a. CLOSE the 3-pole fuse block (energizing PT references up to the control back
panel fuses)
b. CLOSE the 2-pole breaker (energizing the space heater circuit & the controls
back panel 001 fuse)
ClearSky Control Panel (Right) Setup
Phase-C Energization
Summary of Contents for ClearSky Plus
Page 21: ...Resources 21 ...
Page 22: ...Resources 22 ...
Page 28: ...Design Considerations 28 myPV ClearSky PLUS 25kV Termination Cabinet Door Swing ...
Page 38: ...Receiving 38 Equipment is Wrapped Palletized Typically Equipment Delivery ...
Page 45: ...Receiving 45 Top Fuse Mounting Hardware Three 3 MV Fuses Fully Assembled Installed ...
Page 52: ...Electrical Terminations 52 LV Termination Cabinet ...
Page 56: ...Network Integration 56 ...
Page 64: ...Pre Energization Checks 64 View of Center Switching Cabinet Through Wire Glass Window ...
Page 67: ...Pre Energization Checks 67 View of Three 3 PT Fuses Through Wire Glass Window ...
Page 93: ...Operational Testing 93 Numbered Illustration of Protective Relay Indicators ...
Page 102: ...Spare Parts 102 ...
Page 103: ...Spare Parts 103 ...