Commercial Operation
100
Inspection
Description
Every
(Yrs)
Outage
Following isolation and LOTO, the Utility side MV Termination
cabinet should be opened to: 1. Inspect that it is free of debris,
water, animals, or other contamination 2. MV elbows are firmly
seated 3. MV conductors are fee of defects 4. All grounds and
bleed wires are intact 5. Electrical conduits are sealed 1. If
contamination is observed, the cabinet should be cleaned. If
unseated, MV elbows should be removed, new silicon applied,
and re-seated.If damaged, MV conductors should be
services/replaced by a qualified party. If poor/un-grounded,
grounds should be repaired and tested.If unsealed, conduits
should be re-sealed.
2
Following isolation and LOTO, the Solar side MV Termination
cabinet should be opened to: 1. Inspect that it is free of debris,
water, animals, or other contamination 2. MV elbows are firmly
seated 3. MV conductors are free of defects 4. All grounds and
bleed wires are intact 5. Electrical conduits are sealed 1. If
contamination is observed, the cabinet should be cleaned.If
unseated, MV elbows should be removed, new silicon applied,
and re-seated.If damaged, MV conductors should be
serviced/replaced by a qualified party. If poor/un-grounded,
grounds should be repaired and tested. If unsealed, conduits
should be re-sealed.
2
Summary of Contents for ClearSky Plus
Page 21: ...Resources 21 ...
Page 22: ...Resources 22 ...
Page 28: ...Design Considerations 28 myPV ClearSky PLUS 25kV Termination Cabinet Door Swing ...
Page 38: ...Receiving 38 Equipment is Wrapped Palletized Typically Equipment Delivery ...
Page 45: ...Receiving 45 Top Fuse Mounting Hardware Three 3 MV Fuses Fully Assembled Installed ...
Page 52: ...Electrical Terminations 52 LV Termination Cabinet ...
Page 56: ...Network Integration 56 ...
Page 64: ...Pre Energization Checks 64 View of Center Switching Cabinet Through Wire Glass Window ...
Page 67: ...Pre Energization Checks 67 View of Three 3 PT Fuses Through Wire Glass Window ...
Page 93: ...Operational Testing 93 Numbered Illustration of Protective Relay Indicators ...
Page 102: ...Spare Parts 102 ...
Page 103: ...Spare Parts 103 ...