15
79D0004
Lo-Rider Designer Vent Free Fireboxes
WirinG to JunCtion box & Glass CleaninG
forCeD air kit
If you are installing the forced air kit Model BlOTDl on the lSTF36, lPF36, gCRF36 or gClF36
units, see the installation instructions below supplied with kit.
WirinG to JunCtion box
note: the wire must be run to the junction box before framing the firebox.
1. wire the receptacle into an electrical circuit. Use minimum 60°C wire in accordance to pre-
vailing codes.
2. The junction box is preinstalled at the factory. Remove junction box cover by removing the
screw from the outside firebox wall.
3. The junction box cover has a factory-installed “romex” style strain relief connector. Connect
the wires according to the wiring diagram below. Route the connected wire leads through
the strain relief connector.
Figure 20
figure 20a -
Wiring Diagram for Junction box
Glass CleaninG
note: Glass should not be removed for cleaning
When Cleaning Glass
•
Allow glass to cool before cleaning.
•
Never use abrasive cleaning materials on glass.
•
Keep children and pets at safe distance away.
•
Never operate fireplace if glass is broken. Replace any glass that is chipped, cracked or
broken. Replacement glass frame assemblies MUST be supplied by the fireplace manu-
facturer.
Do not substitute other materials.
•
Handle glass frame with care. Avoid striking or scratching glass on hard objects.
figure 20b -
Wiring Diagram for blower
note
: For see thru and peninsula
models, two blower kits may be used
and will be controlled independently.
C
aution
electrical connections should only be performed by a qualified,
licensed electrician, main power must be off when connecting to
main electrical power supply or performing service.
the blower when installed, must be electrically grounded in
accordance with local codes or in the absence of local codes, with
the national electrical Code ansi/nfpa 70.
120VAC
Receptacle
Junction Box
BLACK
GREEN
TAN
TAN
WHITE
BLACK
BLACK
Speed Control
Optional Thermostatic Switch