COMMISSIONING
Table 12 shows a list of points that need to be checked after installation.
Table 12 - Commissioning steps procedure
Description
Check all power connection are tightened with 20 Nm.
Check all CAN-bus cables are connected of the battery modules.
Check CAN-bus termination resistors are installed if applicable.
Perform a charge/discharge test run and measure the temperature of the battery
terminals during the test. Check for excessive heat generation in the system.
NOTICE:
For system commissioning procedure, refer to the manual of the MG Master LV or
MG Master HV. If no commissioning procedure is available in the manual, contact
MG Energy Systems.