Verifying Installation
Verifying installation of the 4700 consists of making sure that it starts up properly and that the
network connections are operational.
8.1
Verifying Start-up Operations
To verify that the 4700 starts up properly:
1.
Observe the power supply LEDs on the fans module front panel to make sure the power
supplies are operable.
2.
Listen and check for airflow to make sure the fan assembly is operating.
3.
Observe system LEDs to verify that the system is running and operational.
4.
If any of these conditions are not met, refer to Troubleshooting to isolate and if possible
resolve the problem.
8.2
Verifying Network Connections
Verifying the network connections consists of making sure that the following network ports
are operational:
InfiniBand
10/100/1G Ethernet management
8.3
Where to Go Next
Once you have verified that the 4700 hardware is properly installed, it is ready for optional
system configuration.
To configure the system software, refer to
Mellanox Grid Director 4000 Family User Manual
.
8.4
Troubleshooting
8.4.1
Solving Operation Problems
When a startup problem is encountered, it is usually attributed to a single component, which is
more difficult to isolate than a problem to a subsystem.
When troubleshooting, we suggest that you start by troubleshooting each separate subsystem
in the 4700, since there are fewer subsystems than components.
The 4700 chassis consists of the following subsystems:
Power supplies that operate whenever system power is connected