INSTALLATION
1) Assemble Zero Clearance box as per instructions
on page 6.
DOT NOT INSTALL FRONT PLATE.
2) Place the unit on the stand-offs in the Zero Clear-
ance box.
3) Slide the unit in all the way back.
4) Run required gas and electrical connections to the
Zero Clearance box, both are located on the left
hand side of the unit. See "Gas Supply Line" on
page 9 and "Electrical Supply" on page 9.
5) Attach flue collar to the top assembly. Align with
holes in Zero Clearance box and secure with 4
screws.
6) Install front panel of zero clearance box, secure
using 6 screws.
7) Make the final gas and electrical connections as
per the instruction manual.
Zero Clearance Box
with unit in place.
Zero Clearance Box assembled.
ZERO CLEARANCE
BOX INSTALLATION