© Martin Engineering GmbH
26
M3289UK-01/17
Installation
5.3
Test run
1.
Thoroughly clean the external chute wall on the operator side
above the tensioner. Affix Conveyor Products Warning Labels
(Part No. 23395) close to the product where they can be seen
by the system operator (also refer to Fig. 13 on page 28).
2.
Remove all tools and fire protection covers from the installation
site and the conveyor belt.
3.
Perform a 1-hour test run of the conveyor system.
4.
Shut off the conveyor system after the test run, shut off the
power supply and secure it against unauthorised reactivation.
5.
Check whether all of the fastening parts are securely tightened.
Tighten any loose connections.
NOTE
Read through this section completely before starting any work on
the belt cleaner or on the customer's conveyor system.
CAUTION! FLYING OBJECTS!
Forgotten tools or installation parts can fall off of the running
conveyor belt and cause minor injuries and property damage.
Always remove any tools from the installation site and conveyor
belt upon completion of the installation work before switching on
the power supply.
WARNING! RISK OF INJURY!
Body parts and/or clothing may get caught and pulled in by
rotating parts or by the moving conveyor belt.
Before any installation or maintenance work is carried out, ensure
that all power sources to the conveyor belt system and its
accessories are switched off and secured against unauthorised
reactivation.
Use warning signs!
CAUTION! RISK OF DAMAGE!
Never operate the belt cleaner for longer than 15 minutes on the
running, unloaded conveyor belt. A risk of damage due to
overheating exists for the belt cleaner and/or the conveyor belt.
Only operate the belt cleaneron a running and fully loaded
conveyor belt.