Preparing for the installation
4
Preparing for the installation
4.1
Before the installation
4.1.1
Required materials and tools
No special tools are required for the installation and maintenance of
the product.
4.1.2
Preparatory measures
1.
Inspect the delivery for the following conditions:
•
Is the delivery complete? Does the number of pallets/
crates/containers delivered match the number on the
delivery note?
•
Do all of the transport packages appear to be undamaged?
Does damage to the packaging exist which indicates
damage to the product contained inside?
2.
Always record any incompleteness or transport damage
discovered in the delivery and have it confirmed by the shipper.
All damaged products must be kept for inspection.
3.
The delivery should include the following parts, depending on
the scope of the order:
•
Brush cleaners incl. two tensioners.
•
Two Conveyor Products Warning Labels:
Part no. 23395
•
Installation instructions
4.
Report any missing or damaged parts to Martin Engineering or
one of its authorised dealers.
NOTE
Perform the inspections carefully and completely as described.
The shipping company is liable for any transport damage!
Please contact the shipper with any damage claims.
NOTE
An unfavourably or improperly installed product can disrupt the
conveyor process or contaminate the bulk material to be
transported.
The owner-operator is responsible for taking the required
countermeasures.
In the case of applications with contaminants, please seek the
advice of Martin Engineering or
one of its representatives.