001223MAN-05
1-Jul-2017
GENERAL MAINTENANCE SCHEDULE
Item
Interval
Procedure
Air Filter
6 months
Inspect for dirt. Replace if necessary.
Contactor
1 year
Inspect for pitted or burned points. Replace if necessary.
Condensate Drain
1 year
Inspect for clogs. Remove and clean if necessary.
Heat exchanger
As required*
Clean as per HEAT EXHCANGER FLUSING PROCEDURE below.
*Generally not required for closed loop systems. Whenever system performance is reduced for open loop.
COAXIAL HEAT EXCHANGER FLUSHING PROCEDURE—GROUNDWATER
STEP 1
Isolate the heat exchanger by closing the valves in the IN and OUT ports to the heat exchanger.
STEP 2
Blow out the heat exchanger into a clean 5 gallon bucket using compressed air.
STEP 3
If a purge cart is not available, use a 5 gallon plastic bucket, a circulator and some plastic piping to create a
makeshift pump system. Connect a the inlet and outlet to the heat exchanger ports.*
STEP 4
Place 2 gallons of RYDLYME in the purge cart (or bucket). Circulate the fluid through the heat exchanger
for at least 2 hours (3 recommended).
STEP 5
Disconnect the purge system dispose of the solution. RYDLYME is non-toxic and biodegradable and as
such can be poured down a drain.
*
Depending on the plumbing, there should be either unions or boiler drains for to access the heat exchanger.
STEP 6
Connect fresh water and a drain to the heat exchanger ports and flush the exchanger for several minutes.
STEP 7
Return the plumbing to its original configuration and open the IN and OUT valves. Operate the system and
check for improved performance.
COAXIAL HEAT EXCHANGER FLUSHING PROCEDURE—GROUND LOOP
STEP 1
Isolate the heat exchanger by placing the pump module valves in the exchanger flushing position.
STEP 2
Connect a compressed air and a drain pipe to the pump module purge ports and blow the anti-freeze solu-
tion into a clean 5 gallon bucket.
STEP 3
Connect a purge cart to the pump module purge ports.
STEP 4
Place 2 gallons of RYDLYME in the purge cart. Circulate the fluid through the heat exchanger for at least 2
hours (3 recommended).
STEP 5
Disconnect the purge cart and dispose of the solution. RYDLYME is non-toxic and biodegradable and as
such can be poured down a drain. Clean the purge cart thoroughly.
*
Depending on the plumbing, there should be either unions or boiler drains for to access the heat exchanger.
STEP 6
Connect fresh water and a drain to the pump module purge ports and flush the exchanger for several
minutes.
STEP 7
Blow the heat exchanger out with compressed air as per STEP 2 and dump the water down a drain.
STEP 8
Connect the purge cart to the pump module purge ports. Re-fill and purge the heat exchanger with as per
standard procedures (the anti-freeze from STEP 2 can be re-used).
STEP 9
Disconnect the purge cart and set the pump module valves back to the original positions.
STEP 10
Operate the system and check for improved performance.
General Maintenance
Summary of Contents for TF-45
Page 12: ...Page 12 001223MAN 05 1 Jul 2017 ...
Page 13: ...1 Jul 2017 Page 13 001223MAN 05 ...
Page 14: ...Page 14 001223MAN 05 1 Jul 2017 ...
Page 15: ...1 Jul 2017 Page 15 001223MAN 05 ...
Page 16: ...Page 16 001223MAN 05 1 Jul 2017 ...
Page 19: ...1 Jul 2017 Page 19 001223MAN 05 ...
Page 20: ...Page 20 001223MAN 05 1 Jul 2017 ...
Page 23: ...1 Jul 2017 Page 23 001223MAN 05 ...
Page 24: ...Page 24 001223MAN 05 1 Jul 2017 ...
Page 25: ...1 Jul 2017 Page 25 001223MAN 05 ...
Page 26: ...Page 26 001223MAN 05 1 Jul 2017 ...
Page 27: ...1 Jul 2017 Page 27 001223MAN 05 ...
Page 30: ...Page 30 001223MAN 05 1 Jul 2017 ...
Page 31: ...1 Jul 2017 Page 31 001223MAN 05 ...
Page 32: ...Page 32 001223MAN 05 1 Jul 2017 ...
Page 33: ...1 Jul 2017 Page 33 001223MAN 05 ...
Page 34: ...Page 34 001223MAN 05 1 Jul 2017 ...
Page 38: ...Page 38 001223MAN 05 1 Jul 2017 ...
Page 39: ...1 Jul 2017 Page 39 001223MAN 05 ...
Page 40: ...Page 40 001223MAN 05 1 Jul 2017 ...
Page 74: ...Page 74 001223MAN 05 1 Jul 2017 Wiring Diagram 208 230 1 60 ...
Page 75: ...1 Jul 2017 Page 75 001223MAN 05 Electrical Box Layout 208 230 1 60 ...
Page 76: ...Page 76 001223MAN 05 1 Jul 2017 Wiring Diagram 208 3 60 ...
Page 77: ...1 Jul 2017 Page 77 001223MAN 05 Electrical Box Layout 208 3 60 ...
Page 78: ...Page 78 001223MAN 05 1 Jul 2017 Wiring Diagram 460 3 60 ...
Page 79: ...1 Jul 2017 Page 79 001223MAN 05 Electrical Box Layout 460 3 60 ...
Page 80: ...Page 80 001223MAN 05 1 Jul 2017 Wiring Diagram 220 1 50 ...
Page 81: ...1 Jul 2017 Page 81 001223MAN 05 Electrical Box Layout 220 1 50 ...
Page 82: ...Page 82 001223MAN 05 1 Jul 2017 ...
Page 83: ...1 Jul 2017 Page 83 001223MAN 05 ...
Page 84: ...Page 84 001223MAN 05 1 Jul 2017 ...
Page 85: ...1 Jul 2017 Page 85 001223MAN 05 Dimensions TF 45 Left Return ...
Page 86: ...Page 86 001223MAN 05 1 Jul 2017 Dimensions TF 45 Right Return ...
Page 87: ...1 Jul 2017 Page 87 001223MAN 05 Dimensions TF 55 65 75 80 Left Return ...
Page 88: ...Page 88 001223MAN 05 1 Jul 2017 Dimensions TF 55 65 75 80 Right Return ...