BOXER SERIES80-120 KVA
INSTALLATION
AG-SD-37/ Publication Date: 19.10.2012/Rev. No:1/Rev. Date:16.11.2012
24
3.1.2 Pre-Installation Check Up
Before installing the UPS product, the following checks should be carried on. These are the first
and important steps in the operation of the product correctly.
Definitely check whether or not any damage was done to internal and external structures
of the UPS, accessories and batteries during transportation or shipment. Report any
damages before receiving.
Make sure that the product is the right model. Check whether the label behind the device
matches with the product ordered or not.
3.1.3 Positioning
The UPS and the batteries are designed for indoor use, and must be placed on a clean area with
cool air flow.
3.1.3.1 Positioning the UPS
For the Boxer 80-120 KVA Series, fresh and cool air enters the device from the front side and
goes out through the fans on the top side of the device. Air entrance and exit points should never
be closed. It must be positioned on a place where is protected from water or similar liquid
contact risks.
If the area is very dusty, filters optional provided must be used. Usage of these filters must be
done according to the relevant instructions.
The UPS is structurally a losing-energy system. Lost energy occurs as heat emissions. The
requirements to the cooling system provided in the following table. Using the table, what
capacity of air conditioned should be used to cool the place where the UPS is can be determined.
Device
BTU/h amount for
cooling
Estimated BTU/h value
For 100%Bridge Load
(Non-Linear Load)
Operation
80KVA
17500
21000
100KVA
21600
25900
120KVA
26300
31500