Lucent Technologies Lineage
®
2000 ECS-6 Controller J85501D-1
Issue 6 August 1998
Acceptance Testing 5 - 1
5
Acceptance Testing
Test Procedures
The ECS-6 controller is tested as a unit and as a part of a battery
plant system in the factory. This section of the manual is
provided for those users who wish to repeat some of those test
procedures as part of the installation and turn-up process. Most
of these tests should not be performed while the plant is
powering active loads.
The test procedures in this section are listed below.
•
Meter Calibration
•
Battery on Discharge Alarm*
•
Float and Equalize Control
•
High Voltage Shutdown and Restart*
•
Fuse Alarm*
•
Remote On/Off (TR signal)*
•
Bulk Ringer Alarm*
•
Low Voltage Battery Disconnect*
*These tests are not suitable for plants in service.
Test equipment required:
•
Test load - 5 kW minimum (60V minimum for 48V plants;
30V minimum for 24V plants)
•
Multimeter
•
Jeweler’s screwdriver
•
Flat-blade screwdriver
•
Blown fuse (Bussman GMT type)
•
Resistor, 4.64K ohm, 2W minimum, 10%
•
Short length of 22 to 26-gauge wire, 4" (100 mm) maximum
•
Power supply, adjustable 0-60 volts dc, 1 ampere, with clip
leads