3-3. Secure installation service space
1) Before installation of the turbo chiller, secure enough space for service as indicated in the foundation drawings.
It is a minimum space needed for maintenance.
2) For installation of the Centrifugal Chiller, the installation must be robust to withstand the operation weight of the
Centrifugal chiller according to the specifications indicated in the basic drawings.
3) Provide a good drainage path to drain out the water when cleaning the heat transfer tubes as well as for draining
cold water and cooling water before shutting down.
4) To ensure the stable operation of the Centrifugal chiller, level off the Centrifugal chiller by adjusting the leveling
plates during the installation. (Maintain 0.5 mm for each 1 m)
5) Basic construction is out of scope of LG Electronics. Please work according to the approved foundation drawings.
LG Electronics is not responsible for any equipment problems due to inappropriate foundation design and construc-
tion.
܆ॄȰێ
QLUPP
RLQPP
QLUPP
QLPPP
Fig 4. Minimum space required for installation
Product Height