- 44 -
1. Form the piping according to its routing. Avoid
bending and bending back the same piping point
more than three times. (This will result in hard-
ening the pipe.)
2. After deforming the piping, align centers of the
union fitting of the indoor unit and the piping, and
tighten them firmly with wrenches.
3. Connect pipe to the service valve or ball valve
which is located below the outdoor unit.
4. After completing the piping connection, be sure
to check if there is gas leakage in indoor and
outdoor connection.
After completing the piping connection, execute
vacuum drying for the connecting piping and the
indoor unit.
The vacuum drying must be carried out using the
service ports of both the liquid and gas side valves.
Use two wrenches and tighten with regular torque.
Outdoor
unit
Liquid side
Flare connection
Flare connection
Gas side
Indoor
unit
Union
Piping Connection
Vacuum drying
CAUTION
Flare nut fastening torque
Ø6.35mm(1/4")
1.8kg.mm
Ø9.52mm(3/8")
4.0kg.mm
Ø12.7mm(1/2")
5.5kg.mm
Ø15.88mm(5/8")
6.6kg.mm
Summary of Contents for HPCI-C35E
Page 110: ... 110 Electronic Control Device 1 Room Type Indoor Unit MAIN P C B DC ASM MAIN P C B AC ASM ...
Page 111: ... 111 2 Cassette Type Indoor Unit MAIN P C B DC ASM ...
Page 112: ... 112 3 Convertible Type Indoor Unit ...
Page 113: ...4 Duct Type Indoor Unit 9 12k 113 ...
Page 114: ... 114 18k ...
Page 115: ... 115 5 Display ASSY Room Type Indoor Unit Convertible Type Indoor Unit ...
Page 116: ... 116 6 Outdoor Unit MAIN P C B ASM V P U N W ...
Page 117: ... 117 Schematic Diagram 1 Room Type Indoor Unit ...
Page 119: ... 119 3 Convertible Type Indoor Unit RY 4WAY RY OUTFAN ...
Page 139: ...P No 3828A20097S February 2004 Printed in Korea ...