Commissioning
Commissioning steps (overview)
Control via digital inputs
60
EDBCSXE040 EN 6.0
6.1.3
Control via digital inputs
Note!
Follow the commissioning steps in the given order!
Setting
Short description
Detailed
information
Initial state:
l
Basic settings completed.
l
C0001 = 1
1.
Set input X6/DI2 to HIGH.
Output X6/DO1 is set to HIGH when the module
is ready for operation.
2.
Set input X6/DI1 to HIGH.
Charging process is started.
After some seconds the earth−fault test is complete and the DC bus is charged. The power
supply module is now ready for operation (status word 1, bit 0 = 1).