11.4
Initial switch-on
Please do not change the switch-on sequence explained below!
Stop!
Prior to initial switch-on of the controller, check the wiring for
•
completeness
•
short-circuit
•
earth fault
1. Switch on the controller and, if necessary, the external supply of the 2175 fieldbus module.
– A controller status LED (
(
^
10-1)
, pos. 3 ) must now be on or blinking. If this is not the case,
see chapter ” Troubleshooting”
(
^
13-1)
– The green LED (” Controller connection status” ) must be on, too
(
^
10-1)
(pos. 1). If this is not
the case, see chapter ” Troubleshooting”
(
^
13-1)
.
2. It should now be possible to communicate with the drive:
– All parameters (SDO) can be read and written
– All SDO parameters except process data, such as frequency setpoint or control word, can
be overwritten.
– For more information on the communication phases of the CAN network see chapter 6.1.2
(
^