background image

Page 12

B – Evacuating the System

 1– Attach gauge manifold. Connect vacuum pump (with

vacuum gauge) to center port of gauge manifold.
With both manifold service valves open, start pump
and evacuate indoor coil and refrigerant lines.

IMPORTANT

A temperature vacuum gauge, mercury vacuum
(U–tube), or thermocouple gauge should be used.
The usual Bourdon tube gauges are not accurate
enough in the vacuum range.

IMPORTANT

The compressor should never be used to evacuate
a refrigeration or air conditioning system.

 2– Evacuate the system to 29 inches (737mm) vacuum.

During the early stages of evacuation, it is desirable
to stop the vacuum pump at least once to determine
if there is a rapid loss of vacuum. A rapid loss of
vacuum would indicate a leak in the system and a
repeat of the leak testing section would be necessary.

 3– After evacuating system to 29 inches (737mm), close

gauge manifold valves to center port, stop vacuum
pump and disconnect from gauge manifold. Attach
an upright nitrogen drum to center port of gauge
manifold and open drum valve slightly to purge line
at manifold. Break vacuum in system with nitrogen
pressure by opening manifold high pressure valve.
Close manifold high pressure valve to center port.

 4– Close nitrogen drum valve and disconnect from

gauge manifold center port. Release nitrogen
pressure from system.

 5– Connect vacuum pump to gauge manifold center

port. Evacuate system through manifold service
valves until vacuum in system does not rise above
29.7 inches (754mm) mercury (5mm absolute
pressure) within a 20–minute period after stopping
vacuum pump.

 6– After evacuation is complete, close manifold center

port, and connect refrigerant drum. Pressurize
system slightly with refrigerant to break vacuum.

C – Leak Testing (To Be Done Only After

Pump Down)

 1– Attach gauge manifold and connect a drum of dry

nitrogen to center port of gauge manifold.

 2– Open high pressure valve on gauge manifold and

pressurize line set /indoor coil to 150 psig (1034 kPa).

 3– Check lines and connections for leaks.

 

4– Release nitrogen pressure from the system,

correct any leaks and recheck.

CAUTION

When using dry nitrogen, a pressure reducing
regulator must be used to prevent excessive
pressure in gauge manifold, connecting hoses,
and within the system. Regulator setting must not
exceed 150 psig (1034 kpa). Failure to use a
regulator can cause equipment failure resulting in
injury.

NOTE-If electronic leak detector is used, add a trace of
refrigerant to the nitrogen for detection by the leak
detector.

D – Charging

Charging must be done in the cooling mode. If system
is completely void of refrigerant, the recommended and
most accurate method of charging is to weigh the
refrigerant into the unit according to the total amount
shown on the unit nameplate and in table 8.
Separate discharge and vapor line service ports are
provided outside the unit for connection of gauge
manifold during charging procedure as well as a
suction line service port.

Unit

10HP18

10HP30

10HP48

10HP12

10HP60

10HP42

10HP36 [CAN]

10HP24

10HP REFRIGERANT CHARGE*

TABLE 8

Refrigerant Charge R–22

10HP36

5 lbs. 3 oz.

6 lbs. 2 oz.
7 lbs. 3 oz.

7 lbs. 7 oz.
8 lbs. 3 oz.
9 lbs. 6 oz.

12 lbs. 13 oz.

5 lbs. 6 oz.

7 lbs. 5 oz.

10HP36-4

7 lbs. 14 oz.

If weighing facilities are not available or if unit is just
low on charge, the following procedure applies. RFC
and TXV systems use different charging methods.

1 – Expansion Valve Systems

The following procedures are intended as a general
guide for use with expansion valve systems only. For
best results, indoor temperature should be between 70 

°

F

and 80 

°

F. If outdoor temperature is 60 

°

F (16 

°

C) or above

the approach method of charging is used. If outdoor
temperature is less than 60 

°

F (16 

°

C) the subcooling

method of charging is used. Slight variations in charging
temperature and pressure should be expected. Large
variations may indicate a need for further servicing.

Summary of Contents for Diplomat 10HP12

Page 1: ...ble in sizes ranging from 1 through 5 tons This manual is divided into sections which discuss the major components refrigerant system charging procedure maintenance and operation sequence Canadian spe...

Page 2: ...breaker size amps 35 35 40 50 60 Minimum circuit ampacity 21 5 21 3 25 0 32 2 40 2 Refer to National Electric Code manual to determine wire fuse and disconnect size requirements NOTE Extremes of oper...

Page 3: ...fan side and the compressor side of the capacitor have different MFD ratings See table 1 for dual capacitor ratings TABLE 1 Unit MFD VAC 10HP C12 DUAL CAPACITOR RATING 10HP18 24 and 30 2 10HP42 10HP4...

Page 4: ...ents 1 Timing Pins 30 60 90 Each of these pins provides a different timed interval between defrosts A jumper connects the pins to circuit board pin W1 Table 3 shows the timings of each pin The defrost...

Page 5: ...r to avoid damaging the circuit board 2 Make sure all control terminals are connected as shown on unit wiring diagram before attempting to place control in test mode See NOTE below NOTE Control will n...

Page 6: ...DE ECCENTRIC ROTARY COMPRESSOR INTERNALS ROTOR SHAFT Figure 10 illustrates the four steps in a rotary compressor s continuous intake cycle The spring loaded blade is compressed fully at the beginning...

Page 7: ...re 13 The reversing valve requires no maintenance It is not rebuildable If the reversing valve has failed it must be replaced If replacement is necessary access the reversing valve by removing the con...

Page 8: ...he liquid line and vapor line service valves and gauge ports are accessible from outside of the unit Full service liquid and vapor line valves are used See figures 18 and 19 The service ports are used...

Page 9: ...e stem cap with an adjustable wrench 2 Using service wrench backseat valve a Turn stem counterclockwise until backseated b Tighten firmly 3 Replace stem cap finger tighten then tighten an additional 1...

Page 10: ...L10 41 50 20 30 40 50 3 8 3 4 3 4 3 4 3 4 3 8 3 8 3 8 10HP30 10HP36 L10 65 30 L10 65 40 L10 65 50 30 40 50 3 8 7 8 7 8 7 8 3 8 3 8 10HP42 10HP48 10HP60 Not Available 3 8 1 1 8 Field Fabricate LINE SET...

Page 11: ...ATOR 10HP42 48 AND 60 ONLY DEFROST SWITCH S6 FILTER DRIER W INTERNAL CHECK VALVE MUFFLER LIQUID LINE FROM INDOOR COIL TO OUTDOOR COIL DISCHARGE LINE SERVICE PORT STRAINER LIQUID LINE SERVICE PORT REVE...

Page 12: ...n to center port of gauge manifold 2 Open high pressure valve on gauge manifold and pressurize line set indoor coil to 150 psig 1034 kPa 3 Check lines and connections for leaks 4 Release nitrogen pres...

Page 13: ...eways until liquid pressures in the 200 250 psig range are reached Block outdoor coil one side at a time with cardboard or plastic sheets until proper testing pressures are reached BLOCKING OUTDOOR CO...

Page 14: ...Read liquid line pressure and convert to condensing temperature using temperature pressure conversion chart Condensing temperature read from gauges should be a few degrees warmer than the liquid line...

Page 15: ...TB1 is energized initiating first stage heat from indoor unit 14 If outdoor temperature is below the balance point N O low ambient cut in thermostat S23 will close 15 When S23 is closed W2 of indoor...

Page 16: ...Page 16 10HP WITH ELECTROMECHANICAL THERMOSTAT...

Reviews: