4.4.1
Battery connection and positioning ............................................................................. 39
4.5
UPS INTERNAL BATTERY ASSEMBLY PROCEDURE ........................................................ 40
4.5.1.1
Installation of 9/11Ah 12V – KEOR HPE 60-80kVA .................................................. 40
4.5.1.2
Installation of 12/14Ah 12V – KEOR HPE 60-80kVA ................................................ 51
4.6
ASSEMBLY PROCEDURE EXTERNAL BATTERY ............................................................... 62
4.6.1
External Battery connection and positioning .............................................................. 63
4.6.1.1
Installation of external battery ................................................................................... 64
4.7
CONNECTION OF THE AUXILIARY CABLES ....................................................................... 66
4.7.1
Battery auxiliary contact ................................................................................................ 66
4.7.2
Diesel Generator auxiliary contact ............................................................................... 66
4.7.3
Backfeed .......................................................................................................................... 66
4.8
PROVISION FOR COLD START FUNCTION ......................................................................... 66
4.9
INTERFACES AND EXTERNAL CONNECTIONS .................................................................. 67
4.10
RELAY CARD CONNECTION ................................................................................................. 68
4.11 CONNEXION DE LA EXT-INP .................................................................................................... 69
5
STARTUP AND SHUTDOWN ...................................................................... 70
5.1 PRELIMINARY CHECKS .............................................................................................................. 70
5.2
START-UP PROCEDURE ....................................................................................................... 71
5.3
BASIC TROUBLESHOOTING ................................................................................................. 73
5.4
SHUT-DOWN PROCEDURE ................................................................................................... 73
5.5
SWITCHING PROCEDURE TO MANUAL BYPASS ............................................................... 74
5.6
RESTART FROM MANUAL BYPASS ..................................................................................... 75
LANGUE FRANÇAIS ........................................................................................... 77
1
OBJET .......................................................................................................... 79
2
RÈGLES DE SECURITE ET AVERTISSEMENTS ....................................... 80
2.1
UTILISATION DE L'ASI ........................................................................................................... 80
2.2
VALEURS NOMINALES DE L’ASI .......................................................................................... 81
2.3
AVERTISSEMENTS SPÉCIFIQUES RELATIFS À LA SÉCURITÉ ......................................... 82
2.3.1
Avertissements généraux .............................................................................................. 82
2.3.2
Personnel ........................................................................................................................ 82
2.3.3
Transport et manutention .............................................................................................. 82
2.3.4
Installation ....................................................................................................................... 83
2.3.5
Raccordement électrique ............................................................................................... 84
2.3.6
Fonctionnement .............................................................................................................. 85
Summary of Contents for BSK93
Page 3: ......
Page 5: ......
Page 176: ...UPS user manual Manuel de l utilisateur de l ASI Utilizzo dell UPS 10 OMG38225 REV F ...
Page 278: ...UPS user manual Manuel de l utilisateur de l ASI Utilizzo dell UPS 112 OMG38225 REV F ...
Page 330: ......
Page 644: ...UPS user manual Manuel de l utilisateur de l ASI Utilizzo dell UPS 158 OMP06263 REV B ...
Page 662: ......
Page 976: ...UPS user manual Manuel de l utilisateur de l ASI Utilizzo dell UPS 158 OMP06263 REV B ...
Page 994: ......
Page 996: ......
Page 1235: ...UPS user manual Manuel de l utilisateur de l ASI Utilizzo dell UPS 10 OMW07104 REV A ...
Page 1286: ......
Page 1337: ...UPS user manual Manuel de l utilisateur de l ASI Utilizzo dell UPS 112 OMW07104 REV A ...
Page 1397: ...11 WWW UPS LEGRAND COM UPS CONVENTIONAL UPS ...