LAARS Heating Systems
Page 64
Boiler 1
(Lead/Lag Master)
Boiler 2
Secondary Primary
TB9, pin 7
connect to
TB9, pin 1
TB9, pin 8
connect to
TB9, pin 2
TB9, pin 9
connect to
TB9, pin 3
TB9, pin 10 connect to
TB9, pin 4
TB9, pin 11 connect to
TB9, pin 5
TB9, pin 12 connect to
TB9, pin 6
3. Repeat the process for Boiler 2 and 3, and
Boiler 3 and 4. The connections to the other
boilers follow the pattern we just described.
Use Fig. 79 as your reference.
4. Connect the drain wires from all of the wire
assemblies together and ground the drain wire
on one end of the assembly only.
5. Turn on the power to all of the boilers when
you are finished.
Job I – Set the Parameters Used by the
Lead/Lag System
(This is a Lead/Lag function – do this once for the whole Lead/
Lag system. Use the controller set up as the Lead/Lag Master –
usually the Primary controller on Boiler 1.)
We have already explained how the Lead/Lag
Master controls the operation of the Lead/Lag
system. Your job at this point is to enter the control
values that the Lead/Lag system will use.
Fig. 80 - ‘home’ screen
1. From the ‘home’ screen (Fig. 80), press the
Lead Lag Master button. Figure 81 shows the
screen that follows.
Fig. 81 – Lead/Lag Master Screen
2. Press the Configure button. The display will
present the Lead/Lag Master Configuration
Screen (Fig. 82).
Fig. 82 – Lead/Lag Master Configuration
3. This screen shows the most important settings
for the Lead/Lag system. The settings can be
changed from this screen. Some of them will
require passwords.
Here are the settings on this screen:
Master enable -
Enabled = Lead/Lag system enabled
CH setpoint -
Setpoint for LL Central Heating
CH time of day setpoint -
Separate Time-of-Day Setpoint for Central
Heating (See the material on “About the
‘Time of Day’ Function at the end of this
section)
DHW setpoint -
Setpoint for Domestic Hot Water
Summary of Contents for NTH1000
Page 4: ...LAARS Heating Systems ...
Page 11: ...NeoTherm LC Boilers and Water Heaters Page 7 Fig 6 Dimensions NT 1700 ...
Page 37: ...NeoTherm LC Boilers and Water Heaters Page 33 Fig 21 Ladder Diagram ...
Page 38: ...LAARS Heating Systems Page 34 Fig 22 Wiring Diagram ...
Page 39: ...NeoTherm LC Boilers and Water Heaters Page 35 ...
Page 51: ...NeoTherm LC Boilers and Water Heaters Page 47 Fig 51 Connection Terminals ...
Page 128: ...LAARS Heating Systems Page 124 Fig 140 Machine Frame NT1000 13 3 Parts Illustrations ...
Page 130: ...LAARS Heating Systems Page 126 Fig 143 Machine Frame NT1700 ...
Page 132: ...LAARS Heating Systems Page 128 Fig 145 Burners and Combustion Chamber NT1000 ...
Page 133: ...NeoTherm LC Boilers and Water Heaters Page 129 Fig 146 Burners and Combustion Chamber NT1700 ...
Page 135: ...NeoTherm LC Boilers and Water Heaters Page 131 Fig 149 Burner Detail NT1700 ...
Page 136: ...LAARS Heating Systems Page 132 Fig 150 Electronic Components Fig 151 Condensate Trap NT1000 ...
Page 138: ...LAARS Heating Systems Page 134 This page intentionally left blank ...
Page 139: ...NeoTherm LC Boilers and Water Heaters Page 135 This page intentionally left blank ...