NeoTherm LC Boilers and Water Heaters
Page 15
3.3.3 Vertical Vent Terminal
When the unit is vented through the roof, the vent
must extend at least 3 feet (0.9 m) above the point
at which it penetrates the roof. It must extend at
least 2 feet (0.6 m) higher than any portion of a
building within a horizontal distance of 10 feet (3.0
m), and high enough above the roof line to prevent
blockage from snow. The vent terminal offered with
the NeoTherm LC can be used in both vertical and
horizontal applications. When the combustion air is
taken from the roof, the combustion air must terminate
at least 12” (30 cm) below the vent terminal.
3.3.4 Vertical Combustion Air Terminal
When combustion air is taken from the roof, a field-
supplied rain cap or an elbow arrangement must be
used to prevent entry of rain water. The opening on
the end of the terminal must be at least 12” (30 cm)
above the point at which it penetrates the roof, and
high enough above the roof line to prevent blockage
from snow. When the vent terminates on the roof, the
combustion air must terminate at least 12” (30 cm)
below the vent terminal.
3.3.5 Installations in the Commonwealth
of Massachusetts
In Massachusetts the following items are required
if the side-wall exhaust vent termination is less than
seven (7) feet above finished grade in the area of
the venting, including but not limited to decks and
porches. (From Massachusetts Rules and regulations
248 CMR 5.08.)
1.
Installation of Carbon Monoxide Detectors
At the time of installation of the side wall vented
gas fueled appliance, the installing plumber or
gas-fitter shall observe that a hard-wired carbon
monoxide detector with an alarm battery back-up
is installed on the floor level where the gas appli
-
ance is to be installed. In addition, the installing
plumber or gasfitter shall observe that a battery
operated or hard-wired carbon monoxide detec-
tor with an alarm is installed on each additional
level of the dwelling, building or structure served
by the side-wall horizontally vented gas fueled
equipment. It shall be the responsibility of the
property owner to secure the services of qualified
licensed professionals for installation of hard-
wired carbon monoxide detectors.
a. In the event that the side-wall horizontally
vented gas fueled equipment is installed in a
crawl space or an attic, the hard-wired carbon
monoxide with alarm and battery back-up may
be installed on the next adjacent floor level.
b. In the event that the requirements of the sub-
division cannot be met at the time of completion
of installation, the owner shall have a period of
thirty (30) days to comply with the above re-
quirements, provided, however, that during said
thirty (30) day period, a battery operated carbon
monoxide detector with an alarm be installed.
2.
Approved Carbon Monoxide Detectors
Each carbon monoxide detector shall comply
with NFPA 720 and be ANSI/UL 2034 listed
and IAS certified.
3.
Signage
A metal or plastic identification plate shall be
permanently mounted to the exterior of the
building at a minimum height of eight (8) feet
above grade directly in line with the exhaust
vent terminal for horizontally vented gas fueled
heating appliance or equipment. The sign shall
read, in print no less than one-half (1/2) inch in
size: “GAS VENT DIRECTLY BELOW, KEEP
CLEAR OF ALL OBSTRUCTIONS.”
4.
Inspection
The state or local gas inspector of the side-wall
horizontally vented gas fueled appliance shall
not approve the installation unless, upon inspec-
tion, the inspector observes carbon monoxide
detectors and signage installed in accordance
with the provisions of 248 CMR 5.08(2)(a) 1-4.
3.4
Common Vent Test
Note -
This section does not describe a method
for common venting NeoTherm LC’s. It describes
what must be done when a unit is removed from
a common vent system. NeoTherm LC’s require
special vent systems and fans for common vent.
Contact the factory if you have questions about
common venting NeoTherm LC’s.
When an existing boiler is removed from a common
venting system, the common venting system is
likely to be too large for proper venting of the
appliances remaining connected to it.
At the time of removal of an existing boiler,
the following steps shall be followed with each
appliance remaining connected to the common
venting system placed in operation, while the other
appliances remaining connected to the common
venting system are not in operation.
1. Seal any unused openings in the common
venting system.
2. Visually inspect the venting system for proper
size and horizontal pitch and determine there is
no blockage or restriction, leakage, corrosion or
other deficiencies which could cause an unsafe
condition.
Summary of Contents for NTH1000
Page 4: ...LAARS Heating Systems ...
Page 11: ...NeoTherm LC Boilers and Water Heaters Page 7 Fig 6 Dimensions NT 1700 ...
Page 37: ...NeoTherm LC Boilers and Water Heaters Page 33 Fig 21 Ladder Diagram ...
Page 38: ...LAARS Heating Systems Page 34 Fig 22 Wiring Diagram ...
Page 39: ...NeoTherm LC Boilers and Water Heaters Page 35 ...
Page 51: ...NeoTherm LC Boilers and Water Heaters Page 47 Fig 51 Connection Terminals ...
Page 128: ...LAARS Heating Systems Page 124 Fig 140 Machine Frame NT1000 13 3 Parts Illustrations ...
Page 130: ...LAARS Heating Systems Page 126 Fig 143 Machine Frame NT1700 ...
Page 132: ...LAARS Heating Systems Page 128 Fig 145 Burners and Combustion Chamber NT1000 ...
Page 133: ...NeoTherm LC Boilers and Water Heaters Page 129 Fig 146 Burners and Combustion Chamber NT1700 ...
Page 135: ...NeoTherm LC Boilers and Water Heaters Page 131 Fig 149 Burner Detail NT1700 ...
Page 136: ...LAARS Heating Systems Page 132 Fig 150 Electronic Components Fig 151 Condensate Trap NT1000 ...
Page 138: ...LAARS Heating Systems Page 134 This page intentionally left blank ...
Page 139: ...NeoTherm LC Boilers and Water Heaters Page 135 This page intentionally left blank ...