5 Installation at Site
32 of 72
Ama-Drainer-Box
4.
Align the Y-pipe horizontally. Always observe the installation dimension (see
Fig. Connecting the discharge line).
5.
Connect the Y-pipe (pipe outside diameter 63 mm) with hose 719.02 and hose
clips 733.01 to the discharge line.
1
80
50
715
410.01
591
Ⓐ
Fig. 20:
Connecting the discharge line; setting the installation dimension; dimensions
in [mm]
1
Fitting direction (from inside to outside)
CAUTION
Y-pipe not aligned, installation dimension not complied with
Risk of fracture due to impermissible stresses and strains at the connections!
Submersible motor pump cannot be installed in the collecting tank!
▷
Observe the alignment of the Y-pipe and the installation dimension (see Fig.
Connecting the discharge line).
Summary of Contents for Ama-Drainer-Box
Page 1: ...Automatic Waste Water Lifting Unit Ama Drainer Box Installation Operating Manual ...
Page 64: ...9 Related Documents 64 of 72 Ama Drainer Box ...
Page 69: ......
Page 70: ......
Page 71: ......