Installation next to tanks containing one liquid and foam
•
The top process connection of the bypass chamber must be above the maximum level of
liquid.
•
The bottom process connection of the bypass chamber must be below the lowest measured
level of liquid.
Installation next to tanks containing more than one liquid
•
The top process connection of the bypass chamber must be above the maximum level of
liquid.
•
The bottom process connection of the bypass chamber must be below the lowest measured
level of liquid.
•
Additional process connections are necessary for the liquids to circulate freely along the
length of the bypass chamber.
Figure 2-15: Installation recommendations for bypass chambers that contain more than one liquid