14
UAB KOMFOVENT we reserve the right to make changes without prior notice
RHP STANDARD_21-04
EN
3. MECHANICAL INSTALLATION
3.1. Requirements for Mounting Location and Installation Base
RHP Standard air handling units are designed for ventilation of medium or large commercial or industrial premises (e.g.,
stores, offices, hotels, etc.) where standard air temperature and humidity is maintained. These units are not intended for
transporting solid particles within air flows. Standard equipment air handling units are intended for indoor installation; and
with additional accessories, these units may be mounted outdoors
1
. Air handling units are designed for ambient tempera-
tures from -30 °C to +40 °C.
•
RHP Standard units are not intended for operation in areas with potentially explosive atmos-
pheres. Air handling units are not designed for ventilation and dehumidification of wet areas
(pools, saunas, car washes, etc.).
•
If the AHU is installed in a room with high humidity level, condensate may form on the walls of
the unit at low outdoor temperatures.
An air handling unit must be mounted on a relatively large and sturdy base, based on the weight of the unit and in ac-
cordance with building regulations. Base must be made of reinforced concrete or metal structures. If the unit is not equipped
with adjustable height feet, it must be installed on a flat and level base. Vibration dampening gaskets must be fitted be-
tween the unit and installation base.
The outdoor air handling units must be fixed to the installation base (e.g., metal angle pieces with
rubber vibration dampening gaskets).
Units installed on such base must be levelled in respect to the horizon – deviations shall not exceed 0.3mm for 1m in the
longitudinal direction and 0.5mm for 1m in the transverse direction.
1
Except RHP 400 and RHP 600.