Adjust the operation by using both of the blade automatic control and manual blade control by blade control lev-
er.
(T) Design surface
LEVELING WORK
Leveling work is the operation to finish the ground when the current ground is similar to the design surface.
Select “Cutting & Carry”.
1.
Start the blade automatic control, and drive the machine.
The blade automatically levels the ground.
2.
Start the place higher than the design surface, and carry the cut soil to the lower place to fill there.