26
Step 4: Frame Assembly
Part 1
It is important to assemble the frame on a flat, smooth surface.
A:
Place Swing Wall from Step 3 between 2 Front and Back Walls from Step 1, noticing the wall orientations.
The tops and bottoms of the walls should be flush. Make sure the walls are square then using the pilot holes as
a guide pre-drill with a 3/16” (4.8 mm) drill bit and fasten the Front Wall to the Swing Wall and Swing Wall to the
Back Wall with 4 (WL5) Wafer Lags per side. (fig. 4.1, 4.2 and 4.3)
Fig. 4.2
Fig. 4.1
Flush
Hardware
8 x
Wafer Lag
WL5
Flush
Notice Front
Wall overlaps
Swing Wall
WL5
WL5
Notice Swing Wall
overlaps Back Wall
Front Wall
Back Wall
Swing Wall
Back Wall
Swing Wall
Front Wall
Flush
Flush
Top View
WL5
Fig. 4.3
x 4 per
side
Notice grooves
face inwards
Notice counter sunk
holes on the outside