Solid Joists
When spacing heat detectors at right angles to the solid joists, do not exceed 50-percent of the listed
spacing and mount the detectors at the bottom of the joists.
Figure 7. Heat Detector Spacing for Solid Joists
Figure 8. Reduced Heat Detector Spacing for Solid Joists Construction
Exposed Beams
Exposed beams may impede the flow of fixed temperature heat detectors. Beams are defined as solid
structures extending 4 in. (100 mm) or more down from the ceiling. Beam spacing depends on the depth
of projection from the ceiling and the center-to-center spacing between the beams.
D. Depth
W. Spacing between joist
1. Ceiling
2. Detector
3. Joist
1. Heat detector
2. Joist
S = Listed spacing between DS-HFS detectors
= 50 ft. (15.2 m)
W
D
1
2
3
> 4 in.
(100 mm)
1/2 S
1/2 S
1/2 S
1/2 S
1/4 S
1/4 S
S
1
2
Summary of Contents for DS Series
Page 1: ...K 73 200 Rev AB July 2015 DS Series Addressable Detector Application Guide K 76 1000 ...
Page 2: ......
Page 3: ...July 2016 1 K 76 1000 FOREWORD ...
Page 6: ...K 76 1000 4 July 2016 NOTES ...
Page 7: ...July 2016 5 K 76 1000 OVERVIEW ...
Page 10: ...K 76 1000 8 July 2016 NOTES ...
Page 11: ...July 2016 9 K 76 1000 HEAT DETECTOR SPACING ...
Page 19: ...July 2016 17 K 76 1000 SMOKE DETECTOR SPACING ...
Page 26: ...K 76 1000 24 July 2016 NOTES ...
Page 27: ...July 2016 25 K 76 1000 HEAT DETECTOR APPLICATIONS ...
Page 29: ...July 2016 27 K 76 1000 SMOKE DETECTOR APPLICATIONS ...
Page 31: ...July 2016 29 K 76 1000 AIR DUCT SMOKE DETECTOR APPLICATIONS ...
Page 35: ...July 2016 33 K 76 1000 TESTING AND MAINTENANCE ...
Page 40: ...K 76 1000 38 July 2016 NOTES ...
Page 41: ......