5.10
Backfill the excavation pit
Fill the excavation pit with suitable filling material
(crushed stone ballast with size 0/16 grain, 50 cm all
round), whilst compacting the filling material properly (e.g.
with a vibrating plate) to Dpr ≥ 95% every 30 cm.
For proper fastening, surround the base section with lean
concrete (see lean concrete wedge(1) in the figure).