- 19-
installed parallel to the receiver.
B. Pre-fasten LCS mounting bracket and LCS clamping bracket with inner hexagon screw.
C. Fasten LCS mounting bracket on the bed piece with M5×16 inner hexagon screw.
D. Insert the buckle of LCS mounting bracket and LCS clamping bracket into the mounting slot of
emitter and receiver, pre-fasten M5×20 inner hexagon screw.
E. Adjust the height position of emitter and receiver. The height position should be consistent. The
installation bolts should be tightened properly.
F.
Adjust M5×16 inner hexagon screw
④
to make the emitter and receiver parallel and aligned,
and properly tighten the bolts.
G. After commissioning, fasten all mounting screws and adjusting screws.
3.2.4
Pipe mounting mode (GZ)
Install the emitter and receiver on the machine tool through the pipe mounting bracket. It is
generally applicable to the open pressure machine and four-column hydraulic press. Installing form
as shown in Fig.3.2.4 The installation steps are as follows:
A. Install pipe mounting bracket
l
According to the safety distance and height position, determine the installation position on both
sides of machine tool, drill holes and tap wire, bracket seat to the bed piece of machine tool
with M8x20 inner hexagon screws;
l
Mount the bracket arm on bracket seat with M16x45 hexagon screw;
l
Insert steel pipe in the hole of bracket arm, adjust it to the proper height. Tighten
inner
hexagon screw on the arm.
B. When front-mount mode is used, before the implementation of step C, firstly penetrate the
lower transmission cable of emitter and receiver to the internal hole of LCS pipe-mounting fixing
clamp. When the side-mount mode is used, the step may be omitted.
C. Respectively fasten LCS vibration-reducer of emitter and reciver to LCS pipe-mounting fixing
clamp with M4x20 cross recessed screws according to the graphical directions.
D. Mount LCS pipe-mounting fixing clamp on each steel pipe, tighten M5×25 inner hexagon