- 18-
A. The installation position of emitter and receiver should be determined according to the
calculated safety distance and height. Care should be taken to ensure that the emitter can be
installed parallel to the receiver.
B. As shown in the graphical direction, connect LCS vibration-mounting bracket and LCS
vibration-reducer with M4x8 cross recessed screws.
C. Fasten LCS vibration-mounting bracket on the bed piece with M5x16 inner hexagon screws.
D. Adjust the position of emitter and receiver to make them parallel and aligned and tighten the
installations crews properly.
E. After commissioning, fasten all mounting screws.
3.2.3
Clamping mounting (JZ) (select back clamping or side clamping)
It refers to the installation mode that the emitter and receiver are directly installed on the machine
body with the clamping mounting bracket. It is generally applicable to the occasions where it is not
convenient to adopt the upper and lower
mounting bracket in the framed structure.
Installing form as shown in Fig.3.2.3 The
installation steps are as follows:
①
Emitter/ Receiver
②
LCS mounting bracket
③
M5×16 inner hexagon screw,
Φ
5
elastic/plain washer
④
M5×16 inner hexagon screw
⑤
M5×20 inner hexagon screw,
Φ
5
elastic/plain washer
⑥
LCS clamping bracket
Fig.3.2.3
Clamping mounting (JZ)
A. The installation position of emitter and receiver should be determined according to the
calculated safety distance and height. Care should be taken to ensure that the emitter can be