Figure 4.1 Example shield connection, control connections
Earthing measures
y
The devices are to be fastened to a conductive, earthed backing plate. Earthing
measures to EN61800-5-1 are described in Chapter 4.4.
External components
y
Place larger loads near the power feed.
y
Contactors, relays, solenoid valves (switched inductances) must be wired with
suppressors. The wiring must be directly connected to the respective coil.
y
Any switched inductance should be at least 0.2 m away from the process-
controlled assemblies.
If you require further detailed information about installation, you should consult the KEBA
Helpline, see chapter 1.11.
26
1 Electrical installation
Operation Manual KeDrive D3-DA BG3 and BG4
1804.200B.1-01 Date: 03/2023
Electrical installation
Summary of Contents for KeDrive D3-DA BG3
Page 14: ...14 1 Safety Operation Manual KeDrive D3 DA BG3 and BG4 1804 200B 1 01 Date 03 2023 Safety...
Page 24: ...24 1 Operation Manual KeDrive D3 DA BG3 and BG4 1804 200B 1 01 Date 03 2023...
Page 66: ...66 1 Operation Manual KeDrive D3 DA BG3 and BG4 1804 200B 1 01 Date 03 2023...
Page 78: ...78 1 Appendix Operation Manual KeDrive D3 DA BG3 and BG4 1804 200B 1 01 Date 03 2023 Appendix...
Page 82: ...82 1 Glossary Operation Manual KeDrive D3 DA BG3 and BG4 1804 200B 1 01 Date 03 2023 Glossary...
Page 83: ...83 1 Operation Manual KeDrive D3 DA BG3 and BG4 1804 200B 1 01 Date 03 2023...