92
.
3.25
KaCool D AF –
Comfortable feeling of well-being, thanks to AtmosFeel
Chilled water air conditioning system
Installation and operating instructions
7 Operation and commissioning
7.1 Pre-commissioning checks
Kampmann GmbH can also perform a functional
check (optional). For contact details please refer to
Chapter 1.4 “Customer Service” on page 6.
DANGER!
Before initial commissioning, check whether all
necessary prerequisites are fulfilled to ensure that
the unit can operate safely and properly.
IMPORTANT NOTE!
Refer to the separate instructions for operation
using the Kampmann room controller.
Structural checks:
Is the unit installed mechanically securely?
Are all accessories and the panel securely fitted?
Electrical checks:
Is all cabling laid in accordance with the applicable
regulations?
Are all wires connected in accordance with the electric
wiring diagrams?
Is the protective conductor connected and wired
throughout?
Water-side check:
Is the flow and return pipework properly connected?
Are the valves correctly fitted? (Note the permitted
installation position of the actuators!)
Are all valves and actuators fitted correctly?
Are the shut-off valves on-site open?
Condensation drain (only with units with cooling function):
Has the condensation drain been checked using the water
fed in for test purposes?
Clean the condensation tray before initial commissioning
and remove dirt and site dust.
Check filter:
Check the filter to ensure that it is clean prior to initial
start-up and replace if dirty.