INSTALLATION
It is recommended that all installations are performed by qualified technicians.
Installation Steps
1.
Read the entire ZLM4 and Energiser manuals first!
2.
Design and build the fence. (Beyond the scope of this manual.) Ask your distributor for help if required.
3.
Decide where the energiser, ZLM4 and Keypad are to be mounted. If on an external wall it should be
housed within a weatherproof equipment box, shaded from direct sun.
4.
Remove the lid of the ZLM4 using a 5mm Hex key.
5.
Remove the ZLM4 PCB chassis from the housing by removing the two screws at the top corners.
6.
Mount the housing by using 4 screws through the rear of the box. The box must be mounted to a wall
in such a way that all of the 4 holes in the rear of the case are against the mounting surface.
7.
Replace the PCB chassis.
8.
If using a keypad, remove the rear housing of the keypad and fix it to the wall.
9.
Wire the low voltage cables to the PCB terminals.
10.
Wire the high voltage cable to the PCB terminals.
11.
Set the Jumpers as required
12.
Fit the battery leads to the battery. The Error LED should be blinking twice to show mains fail.
13.
Replace the front cover (lid).
14.
Turn AC power on.
15.
Arm the ZLM4 and Switch on the Energiser if used. The LCD display will now show the zone voltages.
16.
Find and remove any faults on the fence
17.
Test that a short in any zone puts the ZLM4 into alarm and shows the correct Zone