10
JUDO BIOSTAT 25 TGA
Installation
When installing the water treatment device
in the feed-pipe to the water heater, ensure
that the safety valve of the water heater is
located after the water treatment device in
the direction of flow.
4.2
Requirements for the place of
installation
The room where the unit is installed must
be dry and frost free!
Unauthorised persons must not have
access to the water treatment device!
ATTENTION
(see chapter “Safety information and
dangers due to non-compliance”)
–
The ambient temperature must not
exceed 86 °F (30 °C)! At higher tempera-
tures or direct sun radiation the material
can be damaged.
–
We recommend that the water treatment
device is installed after a backwash
protective filter, to prevent particles of
dirt and sand being swept in.
–
Length of the power lead is approxi-
mately 118 inch (3 m).
–
Particularly in the case of small cross-
sections and soft pipe materials, the
water pipes should be supported in the
vicinity of the connecting flange with two
pipe-clamps.
4.2.1 Installation position
ATTENTION
(see chapter “Safety information and
dangers due to non-compliance”)
Always install the water treatment device in
a vertical position (± 5°)!
Unless, impairments of its function can occur.
4.2.2 Power supply
ATTENTION
(see chapter “Safety information and
dangers due to non-compliance”)
A permanent power supply that is not
connected to a light switch must be avai-
lable. If the water treatment device is not
permanently supplied with power, there is
no warning in case of faults, and no water is
treated.
4.2.3 Mounting the built-in rotary
flange
The built-in rotary flange is used as a
connecting element between the pipe and
the water treatment device.
It is suitable for both, horizontally and verti-
cally mounted pipes.
The built-in rotary flange must be
installed in the direction of flow. This is
marked by a cast in arrow (see fig. 1).
If these instructions aren't respected, the
water treatment device doesn't work.
ATTENTION
(see chapter “Safety information and
dangers due to non-compliance”)
The flange surface of the built-in rotary
flange must be in a vertical position! The
built-in rotary flange must be fitted thus that
mechanical stresses cannot occur! Other-
wise mechanical damages can arise at the
built-in rotary flange. This can lead to major
water damages.
In this case, people close to the water treat-
ment device are exposed to a health risk
due to the large quantities of water.
A power connection (120 V, 60 Hz),
which has to be permanently under
voltage, must be available.
A splash proof socket is required for
the power supply, in accordance with
the legal regulations for wet rooms.