This document describes CK721-A hardware, its installation process, and basic commissioning. It is 
divided into the following sections:

General Description

 on page 1

CK721-A Controller

 on page 3

Wiring CK721-A and Other Modules

 on page 6

Basic Commissioning

 on page 8

Maintenance

 on page 13

When unpacking the equipment, carefully inspect the shipping containers as soon as you receive them 
(with the delivery agent present). If a container is damaged, open it immediately, inspect the contents, 
and have the agent make note on the shipping document. Check the purchase order against the 
packing slips to ensure the order is complete.

If the contents of a container are damaged in any way, notify the carrier and your Johnson Controls® 
representative immediately. Report any discrepancies to your Johnson Controls representative. Save 
the packing materials for possible return shipments.

G

ENERAL

 D

ESCRIPTION

See 

Table 1

 for a description of the CK721-A module and supported equipment. 

Table 1: Module Numbers and Descriptions

Model Number

Description

CK721-A

Each CK721-A can support up to 64 logical terminal numbers assigned to reader modules 
and I/O modules.
Total storage capacity: 200,000 cards and 8,000 off-line transactions.

Note:

 When the number of badges exceeds 120,000, the number of access groups should 

be limited to 50,000.
All CK721-A panels are connected to the server via a 10/100Base-T Ethernet network. The 
CK721-A uses the following modules:

1

 RDR2S-A, I8O4, RDR8S, and I32O16.

1. CK721-A firmware V3.3 and higher also allows for use of Legacy S300 devices under P2000 V3.13 or higher. 

S300-DIN-RDR2SA The S300-DIN-RDR2SA (or RDR2S-A) module provides support for up to 2 doors.

S300-DIN-I8O4

The S300-DIN-I8O4 (or I8O4) module provides support for up to 8 inputs and 4 outputs.

S300-DIN-RDR8S

The 300-DIN-RDR8S (or RDR8S) module provides support for up to 8 doors.

S300-DIN-I32O16

The S300-DIN-I32O16 (or I32O16) module provides support for up to 32 inputs and 16 
outputs.

S300-DIN-S

A small enclosure containing a DIN rail, a tamper switch and a power supply. It has room for 
one controller (CK721-A, or S300-DIN-RDR2SA) and for a battery back-up unit.

S300-DIN-L

A large enclosure containing DIN rails, a tamper switch and a power supply. It has room for 
up to three modules (CK721-A, RDR2S-A, or a combination thereof), and for a battery 
back-up unit.

S300-BAT

Battery for uninterruptible power operation for use in S300-DIN-L. Two backup batteries are 
used per enclosure, 12V, 7Ah.

S300-DIN-BRK

Battery bracket kit for either S300-DIN-L or S300-DIN-S.

S300-BAT-2.8AH

Battery for uninterruptible power operation or use in S300-DIN-S. Two backup batteries are 
used per enclosure, 12V, 2.8Ah 

Summary of Contents for CK721-A

Page 1: ...24 10025 237 Revision December 2017 CK721 A Network Controller hardware installation manual...

Page 2: ...erial returns contact the branch if the material was purchased through a Johnson Controls branch or through the Product Sales Operations Team if ordered through the Advanced Order Management System AO...

Page 3: ...nt must be maintained between 13 35 C 55 95 F and relative humidity of 85 5 by the HVAC system Twenty four hour standby power shall be provided for the HVAC system 6 The installer shall incorporate a...

Page 4: ......

Page 5: ...rds and 8 000 off line transactions Note When the number of badges exceeds 120 000 the number of access groups should be limited to 50 000 All CK721 A panels are connected to the server via a 10 100Ba...

Page 6: ...cate 2398 cryptographic module version 2 0 9 from the Open Source Software Institute http www oss institute org CK721 A controller peer to peer User Datagram Protocol UDP broadcast messages are not en...

Page 7: ...g CK721 A to a Terminal Emulator RS232 Serial Null Modem Cable Wiring on page 6 RS232 B KONE serial server elevator or OTIS serial server elevator controller communications port or ThyssenKrupp serial...

Page 8: ...power is not supplied before you remove the lithium battery the realtime clock will be incorrect LEDs POWER ON is steady when power is applied FAULT OFF indicates normal operation ON indicates a gener...

Page 9: ...l and snap on To remove a module pull the white clips two are located at the bottom and one on top of the module then pull the bottom of the module out and lift it up Wiring Between RS485B and the Fie...

Page 10: ...Listed 22 AWG Stranded Hook up wire Limited to within cabinet Listed 18 AWG 3 cond stranded shielded 4000 ft 1215 m All modules connected to a single CK721 A panel must be within 4000 feet of the pan...

Page 11: ...71 latest edition must be followed for installations in Great Britain Additional information is given in the Cardkey Installers Code of Practice Conduit ground cold water pipes unbrazed joints or diss...

Page 12: ...tant Notes As a security precaution Johnson Controls strongly suggests changing the default controller password during the installation process The CK721 A panel must be set up first using Terminal Em...

Page 13: ...you will be following Serial cable between RS232C A J3 of the CK721 A controller and your laptop or PC serial port or Ethernet cable 2 Start your terminal emulator software 3 For serial communication...

Page 14: ...2000 server Version 3 8 Build 57 with SP2 or later These steps set the IP address and netmask the preferred primary comm path and the network polling of the CK721 A which are required for communicatio...

Page 15: ...LAN setting which specifies the frequency in seconds that the CK721 A panel polls the P2000 server during LAN connections The recommended value is 30 seconds The Network Polling Dup value is not curr...

Page 16: ...ondary IP interface Primary Host IP Address User Def The primary IP address used by the primary server network interface An IP address is a 32 bit number that is notated by using four numbers from 0 t...

Page 17: ...1 A 1 Periodically check the continuity of the grounding circuit 2 Perform operational testing monthly check for proper operation 3 Replace the lithium battery every five years or after extended five...

Page 18: ...Impaired Performance Conditions A list of conditions that may cause impaired performance is provided in the following table with reference pages Field Servicing Troubleshoot the CK721 A by substitutin...

Page 19: ...We welcome your comments at BE techpubs security jci com Security Solutions 805 522 5555 www johnsoncontrols com...