background image

EASYPOOL SMART 0 Operating Manual  |  31

Installation and Commissioning

IMPORTANT!

The needle valve is used to adjust the water flow.
The ball valves must be used to stop the water.

NOTICE!

The "insufficient sample water" display responds with 
a maximum 1 second delay.

5.5 Fitting and calibrating sensors

The mounting of sensors to the water sampling station depends 
on the equipment chosen. The handling of all optionally available 
sensors  is  described. The  assembly  locations  are  indicated  by 
stickers. Use the multi-lingual sticker set for this. The graphic on 
the sticker set shows the locations for the adhesive stickers.

3

4 1 0

2

Fig. 5.5.1 Sensor assembly location

a

 pH sensor

b

 REDOX sensor (depending on model)

c

 Free chlorine sensor (depending on model)

d

 Temperature sensor (depending on model)

e

 Conductivity sensor (depending on model)

pH and REDOX electrodes

pH and REDOX electrodes are filled with an electrolyte and must 
always be kept damp. They should therefore only be fitted if the 
water sampling station is already filled with water. Make sure the 
cap is removed from the electrode prior to installation.

Installation

To install the electrodes the ball valves on the water sampling 
station  input  and  output  are  closed  and  the  electrodes  are 
screwed into the top of the water sampling station. The O-ring of 
the electrode seals the system. It is normally sufficient to screw 
them in manually.

NOTICE!

Crystal formation on or in the sensor is not a fault. The 
crystals will dissolve again during operation.

The measuring cables with electrode connectors are factory-fit-
ted to the controller and labelled near the electrode connector 
with "pH" or "REDOX".

IMPORTANT!

The  connector  must  always  be  kept  dry.  Otherwise 
the reading could be corrupted.

Calibration

The electrodes must be operated for approx. 1 hour with pool 
water prior to calibration. They must be removed for calibration. 
To do this the ball valves at the input and output points of the 
water sampling station must be closed.

NOTICE!

This will not loosen the cable from the electrode. The 
connector allows for a rotary movement between the 
electrode and the cable.

Calibration is described in detail in the controller operating man-
ual.

Chlorine measuring cell

The chlorine measuring cell is located directly at the water inlet 
at the bottom right of the water sampling station. It is fitted and 
connected  at  the  factory.  In  the  chlorine  measuring  cell  valve 
balls moved by the water flow ensure continual cleaning of the 
electrodes.

Calibration

Before the chlorine measuring cell is calibrated the sample water 
should  flow  for  at  least  1  hour. A  photometer  or  a  measuring 
instrument according to the DPD method is required for calibra-
tion.
The chlorine measuring cell can only be calibrated if disinfectant 
has already be dosed in the pool circuit. You should therefore run 
the disinfection in manual mode until the chlorine measurement 
shows a deflection. Then stop manual dosing and calibrate the 
chlorine measuring cell.
Calibration is described in detail in the controller operating man-
ual. For zero point calibration the ball valve at the input of the wa-
ter sampling station is closed. Do not adjust the flow adjustment 
valve. For DPD reference measurement a water sample is taken 
directly from the water sampling station. Flush the ball valve well 
with sample water before taking the actual sample.
The chlorine measuring cell calibration should be repeated at the 
latest 4 hours later. This will give the electrodes time to adapt to 
the operating conditions.

NOTICE!

The efficiency of the chlorine is heavily dependent on 
the pH value. Final calibration of the chlorine measur-
ing cell can therefore only take place when the pH 
value has stabilised to its target value.

Summary of Contents for EASYPOOL SMART 02

Page 1: ...02 Water sampling station for private swimming pool applications EN 01 Dosing Conveying Control Liquids Gases Systems Operating Manual Read this operating manual before start up To be retained for fu...

Page 2: ...nstallation and Commissioning 29 5 1 Tools required 29 5 2 Wall mount 29 5 3 Electrical connection 29 5 4 Connection to the pool water circuit 29 5 5 Fitting and calibrating sensors 31 5 6 Starting au...

Page 3: ...safety tips Basic safety precautions should always be followed when install ing and using this electrical equipment These precautions in clude the following WARNING 1 Read and follow all instructions...

Page 4: ...plicable regulations must be observed The operating manuals of prod ucts used in the system must be observed in par ticular the operating manual of the peristaltic pump which is included separately wi...

Page 5: ...re gauge e depending on model and pH electrode f The water sampling station is connected to the swimming pool water system All the items required for inclusion in the system and for disinfection are e...

Page 6: ...42401014 Yes 42401003 REDOX pH value Yes 42401004 Yes 42401000 Active oxygen 42401010 Flow through chlorine electrolysis 0 20 mA Chlorine pH value Yes Yes 42401001 Chlorine pH value Conductivity 0 20...

Page 7: ...rode Output signal 4 20 mA 0 20 or 0 60 mS cm Operating pressure 0 2 3 bar Operating temperature 5 40 C Water requirement approx 45 l h Weight approx 11 kg Hydraulic connections Clamped connection for...

Page 8: ...ity conductiv or inductive with separate measuring amplifier 20 mA type measuring range depending on type of measuring amplifier Digital inputs Early warning level input for disinfectant Warning level...

Page 9: ...hinge pivot from the equipment If both bolts are removed at the same time the upper part and the lower part of the box will fall loose NOTICE The equipment is to be opened only when plugged off the po...

Page 10: ...order no 78402 Terminal Function Analogue power outputs 0 4 20 mA see also chapter 4 10 1 Measurement value output 0 4 20 mA Disinfection 2 3 pH value 4 5 Temperature 6 7 Salt content 8 9 Programmed a...

Page 11: ...no 78404 optional Terminal Function 71 not used 72 73 74 20 mA passively without supply to the sensor Conductivity measurement 75 76 not used 77 78 outputs board order no 78399 Termi nal Output 81 Di...

Page 12: ...z Description Term Cable Remarks a Chlorine measuring cell CS120 51 A red RD platinum Pt 52 A Blue BU Copper Cu purple VT Silver Ag b pH single rod measuring cell 53 white WH Internal lead 54 black BK...

Page 13: ...ater contact 17 18 Description Term Cable Remarks f Disinfection peristaltic pump 88 Brown BN Relay 41 Blue BU N 39 Yellow green YE GN PE g Peristaltic pump pH 90 Brown BN Relay 41 Blue BU N 39 Yellow...

Page 14: ...sample water contact 17 18 Description Term Cable Remarks j Technoline SC 11 14 Flow through chlorine elec trolyses 1 power supply unit 2 control unit 3 cable A N 91190000 4 electrolytic cell 87 88 y...

Page 15: ...contact 17 18 Description Term Cable Remarks j Technoline SC 11 14 Flow through chlorine elec trolyses 1 power supply unit 2 control unit 3 cable A N 91190000 4 electrolytic cell 87 88 yellow YE Relay...

Page 16: ...ine dosing 90 Relay 42 N Description Terminal Remarks m Power supply Conductivity transmitter 45 L 41 N 39 PE m Conductivity measuring cell 78403 78399 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19...

Page 17: ...values are confirmed with the OK button The clock and timer functions are exceptions Their modification does not require any confirmation General rules for entries The values can only be changed with...

Page 18: ...values The input measuring values are examined for Free chlorine pH value REDOX potential Temperature Conductivity In doing so an important element is the calibration of the sen sors NOTICE When set u...

Page 19: ...ufficient reference value 2 only to check the chlorine content after optimization 4 5 2 Measuring input pH value The voltage signal transmitted by the combination electrode is proportional to the pH v...

Page 20: ...this solution a voltage of 12 mV can be displayed theoretically The physical value actually measured is however always different from the theroretical one When the physical value on the display become...

Page 21: ...calibrated the setting can be calculated from the following table The current measured mA is shown in the calibration window A hand held measuring device can be used for the reference measurement 4 6...

Page 22: ...ercentage value the actuator should reach Example a value of 80 operates the automatic controller to a maximum of 80 The algorithm of the automatic control is however computed further on 100 It is to...

Page 23: ...Tv caused by the differential rate drop to 0 even if the actual value keep deviating away from the default one The fact that the control causes the actual value to match the default one is caused main...

Page 24: ...chlorination For shock chlorination the free chlorine controller is switched to manual operation for an adjustable time and an adjustable dosing rate When the time has elapsed the controller automati...

Page 25: ...the logbook 5 7 Clock Setting of date and time 5 8 Timer Setting of control timer 5 9 Password Setting an access code for individual menus 5 10 Service code Setting a code for menu 5 service 5 11 DIN...

Page 26: ...s automatic changeover Menu 5 8 Timer Main menu menu 2 service timer In this menu you can adjust the timer for active oxygen dosing and allocate to individual week days Menu 5 9 and 5 10 code und Serv...

Page 27: ...be switched off in a specific way in menu 2 Service reset press the Switch off key All controllers are set to an output capacity of 0 and all unsaved data is saved to the memory card The controller c...

Page 28: ...MART the last one in the network The resistances are not active in its delivered state The 120 resistor is applied at the PC side via the interface converter The jumper slots are located in the front...

Page 29: ...th a spirit level After assembly put the water sampling station back in the wall bracket and attach the hinges 5 3 Electrical connection All work on the electrical installation must only be carried ou...

Page 30: ...pump and the injection nozzle is included in the supply The suction hose and pressure line should be routed without kinks Note the peristaltic pump entry and exit points Fig 5 4 2 2 Dosing line hose...

Page 31: ...des must be operated for approx 1 hour with pool water prior to calibration They must be removed for calibration To do this the ball valves at the input and output points of the water sampling station...

Page 32: ...oller description Provide the chemical supply for the pH adjustment and disinfec tion in turn by inserting the suction lines in turn into the vessel Note how the dosing starts each time via the perist...

Page 33: ...a container with water Store the electrodes in a frost free environment NOTICE Over long periods of inactivity an oxide layer forms on the copper electrode of the chlorine measuring cell This must be...

Page 34: ...ng of water guiding components Seal replacement Pump hose replacement Injection nozzle maintenance Sensor check Chlorine measuring cell maintenance The chlorine measuring cell is disassembled and visu...

Page 35: ...s and ball valves 38660 Copper electrode flat 22307 Platinum electrode spiral 22306 Silver electrode flat 35506 d Temperature sensor Pt 100 41100022 Table 8 3 Sensors spare parts for sensors and consu...

Page 36: ...drift too large Not activated No Change buffer solution or replace electrode Sensor or single rod measuring cell not compli ant to DIN Standards Check and eventually replace the input sensor Defective...

Page 37: ...he hand measurement is not affected Stabilise the pH reading through appropriate controller adjustment Potential carry over through electrical devices in the pool circuit Compensate potential insert m...

Page 38: ...ation 29 Installation height 29 Installing sensors 31 Insufficient sample water 30 Interruption in operation 33 L Language 27 M Main menu 18 Maintenance 34 Manual operation 24 Measured value alarms 24...

Page 39: ...EASYPOOL SMART 02 Operating Manual 39 Notes Notes...

Page 40: ...40 EASYPOOL SMART 02 Operating Manual Notes...

Page 41: ...dificaci n en la presente mercanc a sin nuestra previa autorizaci n esta declaraci n pierde su validez NL EU overeenstemmingsverklaring Ondergetekende Lutz Jesco GmbH Am Bostelberge 19 30900 Wedemark...

Page 42: ...erties We hereby certify that the product has been cleaned thoroughly inside and outside before returning that it is free of hazardous materi als i e chemical biological toxic flammable and radioactiv...

Page 43: ...scription of fault Type of fault 1 Mechanical fault Premature wear Wearing parts Breakage other damage Corrosion Damage in transit 2 Electrical fault Connections connectors or cables loose Operating c...

Page 44: ......

Reviews: