8
NEW STRALIS MY2016
‒
GUIDELINES FOR BODYBUILDERS
ADBLUE AND SCRT SYSTEM
6.4
MOVING ADBLUE SYSTEM COMPONENTS
–
Printed 692.68.697
–
5 Ed. - Base 03/2019
189106
Figure 3
1.
AdBlue tank
2.
Pumping module (SM)
3.
Dosing module (DM)
4.
Siphon
A < 1000 mm
B < 1000 mm
C > 0
S
≥
10 mm
Note
Distance (A) is to be considered as fixed since the SM is integrated into the AdBlue tank.
In the diagram shown in the Figure 3, it can be seen that the pipes provide an adequate siphoning system in order to prevent any
damage due to possible AdBlue freezing.
The siphon should have an internal collection volume of 12 cm
3
and is to be located below the reference distance of the DM (for
example S = 10 mm).
Note
After moving the AdBlue tank, contact the IVECO Service Network for the software upgrade connected to the management of the
relative system.
Moving the muffler
●
vertically:
Height increases of up to 100 mm are permitted compared to the original installation distance.
Since sufficient air circulation around the muffler must be ensured, there must be a distance of at least 80 mm between its
upper surface and the superstructure.
●
horizontally:
Retractions are permitted which do not involve changes in the original trend of the exhaust gas temperature in the pipes con-
necting to the engine.
The subsequent lengthening of this pipe must be carried out at the centre so as not to change the position of sensors A and B
in relation to the end of the pipe (see Figure 4).
Summary of Contents for Stralis MY 2016
Page 1: ...I S S U E 0 3 2 0 1 9...
Page 3: ...Printed 692 68 697 5 Ed Base 03 2019 UPDATE DATA Section Chapter Description Revision date...
Page 6: ...Printed 692 68 697 5 Ed Base 03 2019...
Page 7: ...Printed 692 68 697 5 Ed Base 03 2019 SECTION 1 GENERAL INFORMATION...
Page 8: ...Printed 692 68 697 5 Ed Base 03 2019...
Page 27: ...Printed 692 68 697 5 Ed Base 03 2019 SECTION 2 CHASSIS INTERVENTIONS...
Page 28: ...Printed 692 68 697 5 Ed Base 03 2019...
Page 87: ...Printed 692 68 697 5 Ed Base 03 2019 SECTION 3 APPLICATIONS OF SUPERSTRUCTURES...
Page 88: ...Printed 692 68 697 5 Ed Base 03 2019...
Page 139: ...Printed 692 68 697 5 Ed Base 03 2019 SECTION 4 POWER TAKE OFFS...
Page 140: ...Printed 692 68 697 5 Ed Base 03 2019...
Page 165: ...Printed 692 68 697 5 Ed Base 03 2019 SECTION 5 ELECTRONIC SUB SYSTEMS...
Page 166: ...Printed 692 68 697 5 Ed Base 03 2019...
Page 225: ...Printed 692 68 697 5 Ed Base 03 2019 SECTION 6 ADBLUE AND SCRT SYSTEM...
Page 226: ...Printed 692 68 697 5 Ed Base 03 2019...
Page 235: ...Printed 692 68 697 5 Ed Base 03 2019 APPENDIX A STRALIS NP CURSOR CNG LNG...