2.2 Receiving the Pump
Inspect the pump as soon as it is received. Carefully check that everything is in good order. Make
notes of damaged or missing items on the receipt and freight bill. File any claims with the transporta-
tion company as soon as possible.
2.2.1 Storage Requirements
Short Term (Less than 6 months)
Goulds normal packaging procedure is designed to protect pump during shipping. Upon receipt, store
in a covered and dry location.
Long Term (More than 6 months)
Preservative treatment of bearings and machined surfaces will be required. Rotate shaft several
times every 3 months. Refer to driver and coupling manufacturers for their long term storage proce-
dures. Store in a covered and dry location.
HINWEIS:
Long term storage treatment may be purchased with initial pump order.
Units with drivers mounted are moved with slings under the pump casing and driver.
2.2.2 Handling
WARNUNG:
Pump and components are heavy. Failure to properly lift and support equipment could re-
sult in serious physical injury, or damage to pumps.
Use care when moving pumps. Lifting equipment must be able to adequately support the entire as-
sembly. Hoist bare pump using suitable hooks through the holes in the frame mounted support or sui-
table slings through the large openings in the casing mounted support.