3.5 Power
On
Once all of the components have been installed in the subsystem and the
host or drive links have been adequately connected, the subsystem can be
powered on.
Check List
BEFORE
powering on the subsystem, please check the following:
Memory module:
Memory modules have been correctly installed
on the controller boards.
BBU:
Make sure BBUs have been installed correctly.
Hard drives:
Hard drives have been correctly installed in the drive
trays.
Drive trays:
All the drive trays, whether or not they contain a hard
drive, have been installed into the subsystem.
DIP switch settings:
All the appropriate DIP switch settings have
been made. The onboard hub has been enabled/disabled (as
required) and the speed of the host or drive loops selected as 4Gb/s
or 2Gb/s (if the need arises for the compatibility with 2Gb/s
devices).
Cable connections:
The subsystem has been correctly connected
to host computer(s), FC switches or HBAs, and SBODs.
Power cables:
The power cords have been connected to the PSUs
on the subsystem and plugged into the main power source.
Ambient temperature:
All the subsystem components have been
acclimated to the surrounding temperature.
Power On Procedure
When powering on the subsystem, please follow these steps:
Step 1.
Power on the Fibre Channel networking devices.
These devices include FC switches, and any other such
devices connected between application servers and storage.
Please refer to the documentation that came with your
networking devices to see the power-on procedure.
3-18
Power
On