INS

TALLER

US

ER

 MAINTEN

AN

CE TECHNI

CI

AN

jumper X40 (Fig. 3-2). Make sure that the On/

Off thermostat contact is of the “clean” type, i.e. 

independent of the mains supply, otherwise the 

electronic adjustment card would be damaged. 

The Mini CRD must be connected to clamps 40 

e 41 eliminating jumper X40 on the P.C.B. (in the 

boiler), (Fig. 3-2).

Important: 

if the Mini CRD is used, arrange 

two separate lines in compliance with current 

regulations regarding electrical systems. Boiler 

pipes must never be used to earth the electric or 

telephone lines. Ensure elimination of this risk 

before making the boiler electrical connections.

1.7  VENTILATION OF THE ROOMS.

In the room in which the boiler is installed it is 

necessary that at least as much air flows as that 

requested for by normal combustion of the gas 

and ventilation of the room. Natural air flow must 

take place directly through:

- permanent openings in the walls of the room 

to ventilate that lead towards the outside;

-  ventilation pipes, individual or branched type.
The air used for ventilation must be withdrawn 

directly from outside, in an area away from 

sources of pollution. Natural air flow is also 

allowed indirectly by air intake from adjoining 

rooms. For further information relative to ven-

tilation of the rooms follow that indicated by the 

standards set and the following modifications 

and integrations.

Evacuation of foul air. 

In the rooms where the 

gas appliances are installed it may also be neces-

sary, as well as the intake of combustion agent air, 

to evacuate foul air, with consequent intake of a 

further equal amount of clean air. This must be 

realised respecting the provisions of the technical 

regulations in force.

1.8  EVACUATION OF COMBUSTION 

PRODUCTS: FLUE DUCT AND 

BRANCHED MULTIPLE FLUES 

The European regulation 813/2013 provides that 

this boiler can be installed only to replace simi-

lar equipment connected to existing branched 

multiple flues. 

Connection to branched multiple flues. 

Fitting the appliances to a branched multiple flues 

takes place by means of flue ducts. 

In the event of fittings with pre-existing flues, 

these must be in safe and efficient status and per-

fectly clean because the detachment of any waste 

from the walls during functioning, could block 

the passage of flue gases, thus causing extremely 

dangerous situations for the user. 

The flue ducts must be connected to the chimney 

or flue in the same room in which the appliance 

is installed or, at most, in the adjoining room and 

must comply with the requirements indicated by 

the current technical regulations.

1.9  FLUE EXHAUST CONTROL DEVICE

Important: 

it is prohibited to put the fumes 

exhaust control device out of order voluntarily. 

Every piece of this device must be replaced using 

original spare parts if they have deteriorated. In 

the case of repeated interventions of the fumes 

exhaust control device, check the fumes exhaust 

flue and the ventilation of the room in which the 

boiler is located.

1.10 SYSTEM FILLING.

Once the boiler is connected, proceed with sy-

stem filling via the filling valve (Fig. 2-2). Filling 

is performed at low speed to ensure release of air 

bubbles in the water via the boiler and heating 

system vents. The boiler has a built-in automatic 

venting valve on the circulator. Open the radiator 

air vent valves. Close radiator vent valves only 

when water escapes from them.

Close the filling valve when the boiler manometer 

indicates approx. 1.2 bar.

N.B.: 

during these operations start up the cir-

culation pump at intervals, acting on the main 

switch positioned on the control panel.

Vent the circulation pump by loosening the front 

cap and keeping the motor running. 

Screw the cap back on after the operation.

1.11 GAS SYSTEM START-UP.

To start up the system, make reference to the 

Standard. 

In particular, for new gas systems:

- open windows and doors;
- avoid presence of sparks or naked flames;
- bleed all air from pipelines;
-  check that the internal system is properly sealed 

according to specifications.

1.12 BOILER START UP (IGNITION).

For the boiler start up (the operations listed 

below must only be performed by qualified per-

sonnel and in the presence of staff only):

-  check that the internal system is properly sealed 

according to specifications;

-  ensure that the type of gas used corresponds to 

boiler settings;

- check that there are no external factors that 

may cause the formation of fuel pockets;

-  switch the boiler on and ensure correct ignition;
- make sure that the gas flow rate and relevant 

pressure values comply with those given in the 

manual (parag. 3.17);

- check the correct ventilation of the rooms;
- check the existing draught during normal 

functioning of the appliance, e.g. a draught 

gauge positioned at the exit of the appliance 

combustion products;

-  check that there is no backflow of combustion 

products into the room, even during functio-

ning of fans;

- ensure that the safety device is engaged in the 

event of gas supply failure and check activation 

time;

- check activation of the main switch located 

upstream from the boiler.

The boiler must not be started up in the event of 

failure to comply with any of the above.

Summary of Contents for Nike Star 24 4 ErP

Page 1: ...Maintenance Technician 1 038183ENG Instantaneous wall hung boilers with open chamber type B and natural draught The European regulation 813 2013 provides that this boiler can be installed only to replace similar equipment connected to existing branched multiple flues ...

Page 2: ...the regulations in force and principles of good practice In compliance with legislation in force the systems must be designed by qualified professionals within the dimensional limits established by the Law Installation and maintenance must be performed in compliance with the regulations in force according to the manufacturer s instructions and by professionally qualified staff intending staff with...

Page 3: ...se cleaning 12 2 11 Decommissioning 12 3 Boiler start up Initial check 13 3 1 Hydraulic layout 13 3 2 Wiring diagram 14 3 3 Troubleshooting 14 3 4 Converting the boiler to other types of gas 14 3 5 Checks following conversion to another type of gas 15 3 6 Possible adjustments 15 3 7 Programming the p C B 15 3 8 Automatic slow ignition function with timed ramp delivery 16 3 9 Chimney sweep function...

Page 4: ...ifically trained staff and original spare parts Do not attempt to modify or repair the appliance alone Failuretocomplywiththeaboveimpliespersonal responsibility and invalidates the warranty Installation regulations installation of these boilers in bedrooms studio flats and bathrooms or in premises where there are wood fired heaters or solid fuel heaters in general and in premises next to or connec...

Page 5: ...anti backflow kit to be used upstream of the cold water inlet connection of the boiler It is also recommended that the heat transfer fluid e g water glycol entered in the primary circuit of the boiler heating circuit complies with the local regulations in force Important to preserve the duration of appliance efficiency features in the presence of water whose features can lead to the deposit of lim...

Page 6: ...r at most in the adjoining room and must comply with the requirements indicated by the current technical regulations 1 9 FLUE EXHAUST CONTROL DEVICE Important it is prohibited to put the fumes exhaust control device out of order voluntarily Every piece of this device must be replaced using original spare parts if they have deteriorated In the case of repeated interventions of the fumes exhaust con...

Page 7: ...rculator has various built in operation modes however the constant curve operation mode must be selected according to the following table Circulating pump LED Description G Y Y Y Y On On On Off Off Do not use G Y Y Y Y On On On On Off Constant curve speed 2 G Y Y Y Y On On On On On Constant curve speed 3 default G Y Y Y Y On On On Off On Constant curve speed 4 Constantcurve thecirculatoroperatesma...

Page 8: ...ospha tedispenserreducestheformationoflime scale and preserves the original heat exchange and domestic hot production water conditions The boiler is predisposed for application of the polyphosphate dispenser kit Connection unit kit Includes pipes fittings and cocks including gas cock to carry out all connections to the boiler system The above mentioned kits are supplied complete with instructions ...

Page 9: ...hot water probe 7 System filling valve 8 Flue safety thermostat 9 Delivery probe 10 Rapid heat exchanger 11 Safety thermostat 12 Combustion chamber 13 Ignition and detection electrodes 14 System expansion vessel 15 Burner 16 Vent valve 17 Manifold 18 System draining valve 19 By pass 20 3 bar safety valve N B connection group optional 1 15 BOILER COMPONENTS ...

Page 10: ...n the vicinity of ducting or devices for flue extraction and relative accessories switch off the appliance and on completion of operations ensure that a qualified technician checks effi ciency of the ducting or other devices Never clean the appliance or connected parts with easily flammable substances Never leave containers or flammable substances in the same environment as the appliance It is pro...

Page 11: ...eset button 1 04 Contacts resistance block The P C B detects a malfunction of the safety thermostat of the flue pressure switch or of the system pressure switch Press the Reset button 1 05 Flow probe anomaly The board detects an anomaly on the flow NTC probe The boiler does not start 1 06 Domestic hot water probe anomaly The board detects an anomaly on the domestic hot water NTC probe In this case...

Page 12: ...ops contact qualified staff for assistance to eliminate possible system leakage 2 8 SYSTEM DRAINING To drain the boiler act on the special draining valve Fig 2 2 e 1 8 Before draining ensure that the filling valve is closed 2 9 ANTI FREEZE PROTECTION The boiler is supplied with an antifreeze function as per standard that activates the function of the pump and the burner when the internal system wa...

Page 13: ...witchtheboileronandensurecorrectignition make sure the gas maximum intermediate and minimum flow rate and pressure values correspond to those given in the handbook par 3 17 checkactivationofthesafetydeviceintheevent of no gas as well as the relative activation time check activation of the main switch located upstream from the boiler check the existing draught during normal functioning of the appli...

Page 14: ...ent interventions of the chimney safety thermostat This can be caused by obstructions in the fumes circuit Check the flue The flue may be obstructed or by height or section not suitable for the boiler Ventilation may be insufficient see room ventilation point Presence of air in the system Check opening of the special automatic vent valve Fig 1 6 Make sure the system pressure and expansion vessel p...

Page 15: ...gas N B to adjust the gas valve remove the plastic cap 6 after adjusting refit the cap Adjustment of the boiler minimum heat output in heating phase N B only proceed after having calibrated the minimum domestic hot water pressure To adjust the minimum heat output during the heatingphase changeparameter 5 increasing the value the pressure increases reducing it the pressure drops The pressure to whi...

Page 16: ...ndard setting P8 3 8 AUTOMATIC SLOW IGNITION FUNCTION WITH TIMED RAMP DELIVERY In the ignition phase the P C B carries out an increasing gas delivery ramp with pressure va lues that depend on the type of gas selected with preset duration This prevents every calibration or precision adjustment of the boiler ignition phase in any conditions of use 3 9 CHIMNEY SWEEP FUNCTION When activated this funct...

Page 17: ...ot water control thermostat inter vention Check that the internal system is properly sealed according to specifications Check the intervention of the device against no gas ionization flame control Intervention time must be less than 10 seconds Visually check for water leaks or oxidation from on connections Visually check that the water safety drain valve is not blocked Check that after discharging...

Page 18: ...18 3 4 3 2 2 4 1 INSTALLER USER MAINTENANCE TECHNICIAN ...

Page 19: ...50 2 10 6 10 1 80 CO at 0 di O2 at Q Nom Min ppm 79 86 151 100 95 137 NOX at 0 di O2 at Q Nom Min ppm 58 12 110 15 97 12 Temperature of fumes at nominal output C 101 106 102 Temperature of fumes at minimum output C 85 85 76 METHANE G20 BUTANE G30 PROPANE G31 HEATING POWER HEATING POWER BURNER GAS FLOW RATE PRESS BURNER NOZZLES BURNER GAS FLOW RATE PRESS BURNER NOZZLES BURNER GAS FLOW RATE PRESS BU...

Page 20: ...kW kcal h 23 6 20296 Domestic hot water adjustable temperature C 35 55 Min pressure dynamic domestic hot water circuit bar 0 3 Domestic hot water circuit max working pressure bar 10 Minimum D H W flow rate l min 2 0 Continuous flow rate T 30 C l min 11 1 Weight of full boiler kg 25 3 Weight of empty boiler kg 24 6 Electric attachment V Hz 230 50 Nominal absorption A 0 3 Installed electric power W ...

Page 21: ...ber CHK Check Cod PIN PIN code Type Type of installation ref CEN TR 1749 Qnw min Minimum heating capacity domestic Qn min Minimum heating capacity heating Qnw max Maximum heating capacity domestic Qn max Maximum heating capacity heating Pn min Minimum heat output Pn max Maximum heat output PMS Maximum pressure system PMW Maximum pressure domestic D Specific flow rate TM Maximum working temperature...

Page 22: ...artial load elmin 0 014 kW Ignition burner energy consumption Pign 0 000 kW In standby mode PSB 0 003 kW Emissions of nitrogen oxides NOX 138 mg kWh For mixed central heating appliances Stated load profile XL Domestic hot water production efficiency ηWH 78 Daily electrical power consumption Qelec 0 119 kWh Daily gas consumption Qfuel 25 631 kWh Contact information IMMERGAS S p A VIA CISA LIGURE 95...

Page 23: ...ementary heat pump From fiche of heat pump Solar contribution and Supplementary heat pump Select smaller value Boiler and supplementary heat pump installed with low temperature heat emitters at 35 C From fiche of heat pump The energy efficiency of the package of products provided far in this fiche may not correspond to its actual energy efficiency once installed in a building as the efficiency is ...

Page 24: ...he energy efficiency of the package of products provided far in this fiche may not correspond to its actual energy efficiency once installed in a building as the efficiency is influenced by further factors such as heal loss in the distribution system and the dimensioning of the products in rela tion to building size and characteristics Seasonal space heating energy efficiency of package Seasonal s...

Page 25: ... contribution From fiche of solar device 1 I 2 1 1 x I 10 x II III I Auxiliary electricity 3 G F E D C B A A A A 27 27 27 28 27 27 27 28 30 30 30 32 33 34 35 36 36 37 38 40 39 50 55 60 65 75 80 85 100 115 123 131 130 150 160 170 163 188 200 213 M L XL XXL 3 2 3 2 The energy efficiency of the package of products provided far in this fiche may not correspond to its actual energy efficiency once inst...

Page 26: ...ncy under colder and warmer climate conditions Colder 0 2 x Warmer 0 4 x Declared load profile Solar contribution From fiche of solar device 1 ___ 2 1 1 x ___ 10 x ____ ____ ____ Auxiliary electricity 3 G F E D C B A A A A 27 27 27 28 27 27 27 28 30 30 30 32 33 34 35 36 36 37 38 40 39 50 55 60 65 75 80 85 100 115 123 131 130 150 160 170 163 188 200 213 M L XL XXL 3 2 3 2 The energy efficiency of t...

Page 27: ...27 ...

Page 28: ...immergas com Immergas S p A 42041 Brescello RE Italy Tel 0522 689011 Fax 0522 680617 Certified company ISO 9001 This instruction booklet is made of ecological paper Cod 1 038183ENG rev ST 002208 001 02 16 Inglese per IRLANDA IE ...

Reviews: