INSTALLATION
13 NIPPLE ASSEMBLY
14 NIPPLE ASSEMBLY AND SEALANT
-
Put the 2nd section in place and clean the bores with a
brush.
-
Clean the nipples (4) and coat them with the lubricant
supplied with the sections.
-
Press in the 2 nipples moderately using a hammer and a
piece of wood.
-
Carefully apply filler on the sealing grooves (5) with a
spatula so as to ensure correct tightness of the boiler
body.
-
Assemble other sections using the same principle.
-
Put the assembly tool in place (not supplied with the
boiler).
-
Tighten gradually so as to bring about simultaneous and
identical closing of both upper and lower connections.
-
Assemble the remaining sections as per the instructions
under Frames 13 to 15.
NEVER ASSEMBLY MORE THAN 4 SECTIONS AT A TIME.
15 SECTION ASSEMBLY
INST
ALLA
TION