GENERAL
a =
500
1600
b=1600
7
BOILER CLEARANCES AND INSTALLATION
The figures indicate the minimum recommended
dimensions for providing easy access around the boiler.
Boiler dimensions are given in mm.
For unassembled boiler bodies leave clearance
equal to dimensions
a
and
b
for assembly tools
(simplified JD tools for boilers with 8 to 14 sections or
JD-TE tools for boilers with 8 to 20 sections or JD-TE
Plus tools for any other model). Note: not supplied
with the boiler, contact supplier of boiler for the hire of
the same if required.
if a = 500mm ; b = 1600mm
if a = 1600mm ; b = 500mm
Multiple Boiler Installations
A clearance of 200mm must be allowed between
boilers when installed in multiple.
No. of boiler sections
8
9
10
11
A mm
970
1058
1146
1234
No. of boiler sections
12
14
16
18
A mm
1322
1498
1674
1850
No. of boiler sections
20
A mm
2026
Note
Please note that boilers installed in or close to rooms in which the atmosphere is polluted by chlorine of fluorine compounds may
be subject to high corrosion.
For example: hairdressing salons, industrial premises (solvents), cooling equipment, etc.
Boilers installed in such locations will not be covered by the guarantee.
* Clearance for water connections side is 400mm.
This may be either right or left hand side.