Procedure
1.
Clip and remove the cable ties
(A)
that secure the power supplies and control canisters to the
shipping bracket.
Note:
Ensure that you do not clip any cables.
2.
Remove the two screws
(B)
that attach the bracket to the rack. See Figure 7 on page 8.
3.
Loosen the three tension screws
(C)
on the shipping bracket.
Figure 6. Cable ties
Installing and configuring the system
7