Page 28
4
Open raw water supply.
T
he pressure switch (permeate) turns on.
The system is filled and the inlet pressure is built up.
The high-pressure pump starts when the required threshold value for
inlet pressure is achieved.
Permeate is produced.
The green LED illuminates.
5
Rinse
out
the preservation solution for at least
10 minutes
.
6
•
Pull out mains plug
.
•
Close raw water supply
.
7
Connect the permeate outlet with the system to be filled.
8
Check the network cable for damage and
insert
the
mains plug
into a
power outlet.
The control device runs a self-test: the green and red LEDs briefly
flash yellow.
The green LED flashes.
The raw water inlet solenoid valve opens.
9
Open raw water supply.
T
he pressure switch (permeate) turns on.
The system starts up and then begins production
The green LED illuminates.