7
Polarization index calculation method : PI= R600/R60;
test connection points for attention
1.
Tested to confirm product safety grounding, try not charged.
2.
Confirm the instrument E end (ground) have been grounded.
3.
The use of G terminal (protection ring) (this machine is of low voltage side of the
screen)
When measuring high insulation resistance, the sample should be in the position a
conductor surface protection between the two measuring end ring, and the conductor
protection ring is connected to the instrument with a test line G side, try to eliminate the
measuring error caused by the surface leakage current, security testing is accurate.
VI. Packing List
No.
Item
Qty
1
Main engine
1
2
Power line
1
3
Red test line
1
4
Black test line
1
5
Green test line
1
6
Red high voltage shielded wire
1