H. FINAL CHECKS BEFORE STARTING BOILER
1. Read Start-Up Procedure, Part 9 in this manual, for proper steps to start boiler. (See Start-Up Report to record
steps for future reference.)
2. Verify the boiler and system are full of water and all system components are correctly set for operation.
3. Fill the condensate trap with water.
4. Verify electrical connections are correct and securely attached.
5. Inspect intake and exhaust piping for signs of deterioration from corrosion, physical damage, or sagging. Verify
intake and exhaust piping are intact and correctly installed per Venting Section (Part 5) and local codes.
I. CASCADE SYSTEM
1. If a single boiler is installed, skip this section.
2. Programming the Master Boiler:
a. Make sure there is no demand for heat being supplied to the boiler.
b. Apply power to the boiler.
c. Enter the system setting program navigation following instructions in Part 10 of this manual.
d. Verify that the cascade address function 15 is set to 0. This sets the Master Boiler’s address as 0.
NOTE: The Master Boiler MUST be addressed as 0.
e. Change cascade mode function 23 to 926 Boiler. This makes it a Master Boiler.
f. Exit the installer menu.
NOTE:
In order for the system to operate properly, the temperature set point of the master must match the
follower boiler set point.
NOTE: READ THE NOTES BELOW BEFORE PROGRAMMING FOLLOWER BOILERS:
The boiler addressed as 1 will share its alarm output with the master boiler.
If one of the follower boilers has an indirect fired water heater connected to it, the address of this boiler
must be 2 or greater.
It is recommended but not necessary to address boilers in the order that they are wired.
No two boilers can have the same address.
It is not required to use all consecutive address numbers. Example: In a 2 boiler system with an indirect
connected to the follower, the follower address would be 2 (address 1 is not used).
3. Programming Follower Boilers:
a. Make sure there is no demand for heat being supplied to the master boiler.
b. Apply power to the follower boiler you are working on.
c. Enter the system settings following instructions in Part 10 of this manual.
d. Set the Cascade Address parameter 15 to 1 for the first follower, 2 for the second follower, etc.,
depending on which boiler you are programming.
e. Change “CASCADE MODE” parameter to “926 BOILER”. This makes the boiler a follower and enables
all data to be transferred between boilers as needed for the system to function to full capability.
f. Exit the system menu.
NOTE:
For the system to operate properly, the temperature set point of the follower must match that of the master
boiler.
Summary of Contents for EL-110
Page 15: ...15 Figure 3 ...
Page 61: ...61 Figure 29 ...
Page 62: ...62 Figure 30 ...
Page 87: ...87 Figure 33 ...
Page 88: ...88 Figure 34 ...
Page 89: ...89 Figure 35 LP 293 A NOTE Parts listed on the following page ...
Page 94: ...94 ...
Page 95: ...95 ...
Page 96: ...96 MAINTENANCE NOTES ...