49
LP- 293 REV. 9.2.14
3. It is recommended to use the shortest length cable that will reach between the boilers and create a neat installation. Do not run
unprotected cables across the floor where they may become wet or damaged. Avoid running communication cables parallel and close
to or against high voltage (120 volt or greater) wiring. HTP recommends that the maximum length of communication bus cables not
exceed 200 feet.
4. Route the communication cables through one of the knockouts in the cabinet.
5. Connect the boilers in a daisy chain configuration as shown below. It is best to wire the boilers using the shortest wire runs rather
than trying to wire them in the order that they are addressed. The communication bus jacks on the customer connection panel are
interchangeable so you can use either one or both in any order to connect the cable.
If you have connected the boilers to each other properly, there will be no open communication connection ports.
Figure 27
– LP-293-GG
Figure 28
– Cascade Resistor Plug Installation Detail
Summary of Contents for EL-110
Page 13: ...13 LP 293 REV 9 2 14 Figure 3 LP 285 B ...
Page 51: ...51 LP 293 REV 9 2 14 Figure 29 Cascade Master and Follower ...
Page 52: ...52 LP 293 REV 9 2 14 Figure 30 ...
Page 53: ...53 LP 293 REV 9 2 14 Figure 31 ...
Page 54: ...54 LP 293 REV 9 2 14 Figure 32 ...
Page 77: ...77 LP 293 REV 9 2 14 Figure 36 ...
Page 78: ...78 LP 293 REV 9 2 14 Figure 37 ...
Page 79: ...79 LP 293 REV 9 2 14 Figure 38 LP 293 A ...
Page 82: ...82 LP 293 REV 9 2 14 ...
Page 83: ...83 LP 293 REV 9 2 14 ...